Construction of headworks of Melamchi water supply project expedited



KATHMANDU: A target has been set to complete head works under the Melamchi Water Supply Project within two months.

Though the headworks had to be completed within December 2020, it was delayed due to coronavirus pandemic.

Information Officer of the Project, Rajendra Prasad Panta, said that they failed to complete the works on the slated time due to disruption of works following COVID-19. He shared that the headworks would be completed within mid-April as the works are being carried out in an expedited manner.

Panta further said that some works related to electricity as well as others are yet to be completed, adding the construction of headworks delayed in lack of a sufficient number of human resources and materials for the same from April 2020.

Locals had stopped the movement of goods-carrying vehicles saying coronavirus infection might spread. Though the construction works were not completely halted, it was slow during the period, he said. Construction of tunnel has now been completed under the project started two decades ago.

The government on Asoj, 2075 had signed a contract agreement to complete the remaining works after the Italian Construction Company – CMC – left the project unattended.

Two water treatment centers have already been constructed in Sundarijal under the project. The Project is designed to divert about 170 MLD of freshwater to Kathmandu Valley from the Melamchi River in the Sindhupalchowk district.

Augmenting this supply by adding about a further 170 MLD each from the Yangri and Larke rivers, which lie in the upstream proximity of Melamchi is also being investigated as future supply sources.

Ministry of Physical Planning and Works (MPPW) is the executing agency for the Project and an autonomous Melamchi Water Supply Development Board, formulated for Project implementation, is the implementing agency.

RSS

Publish Date : 05 February 2021 13:41 PM

Authorities collect Rs 812,000 in traffic enforcement revenue in Jumla

JUMLA: The District Traffic Office, Jumla, has collected Rs 812,000

Two-thirds of RSP delegates abstain from office-bearer election, turnout drops to around 30 percent

CHITWAN: Participation of delegates at the Rastriya Swatantra Party (RSP)

Bipin Acharya elected RSP General Secretary

CHITWAN: Bipin Acharya has been elected General Secretary of the

Sobita Gautam elected RSP vice-president

CHITWAN: Sobita Gautam has been elected vice-chair of the Rastriya

RSP election: Only 1,289 votes cast for office-bearer posts

KATHMANDU: A total of 1,289 votes were cast in the