Funds being secured for Upper Arun Hydel



KATHMANDU: Banks and financial institutions of Nepal have agreed to invest Rs 53.34 billion in the Upper Arun Hydropower Project.

The total estimated cost of the project is around 214.86 billion rupees.

A financing agreement was signed between Chief Executive Officer of Nepal Electricity Authority, Kulman Ghising, and the CEO of HIDCL, Arjun Kumar Gautam and representatives of Nepal Bank, Nepal Banijya Bank and Citizen Investment Trust.

The project with a total capacity of 1061 MW will have 70 percent of the total cost met through loan investment and 30 percent will be equity capital.

Preparations are being made to acquire loans from the World Bank, European Investment Bank and other international financial institutions.

It is a semi-reservoir project based in Bhotkhola rural municipality of Sankhuwasabha district.

The project will produce 4,512 gigawatt hours of electricity per year of which 30 percent will be produced during the dry season.

The goal is to start construction at the end of 2024 and complete it by 2030. At present, the feasibility study of the project has been completed and the work of selecting a consultant for the bid design and construction supervision work is underway, said NEA CEO Ghising.

Publish Date : 16 September 2022 11:30 AM

Kumar Ben appointed as Balen’s Chief Advisor, Asim Shah as Political Advisor

KATHMANDU: Kumar Ben (Kumar Benjankar) has been appointed as Prime

Former Minister Deepak Khadka arrested

KATHMANDU: Former Minister Deepak Khadka and Nepali Congress leader has

Rain likely in Kathmandu Valley today

KATHMANDU: The weather is likely to remain mostly cloudy across

Police on standby from 8 am; additional teams deployed at possible protest sites in Kathmandu

KATHMANDU: In preparation for the demonstrations by the CPN-UML, the

Economic Digest: Nepal’s Business News in a Snap

KATHMANDU: Economic Digest offers a concise yet comprehensive overview of