Bridge constructions in Tanahun miss deadline



TANAHUN: None of the 12 bridge projects started in the previous fiscal year, 2020/21 in Tanahun district has been completed so far.

As per the plan, six out of 12 had to be completed one month ago. COVID-19 and subsequent prohibitory orders are blamed for the delay.

At present, all the bridges are under construction.

Similarly, three of them are scheduled to be over in the next two months and others until next FY, 2022/23, said Om Raj Dhungana, chief of the infrastructure development office.

Progress of the construction of other bridges is however satisfactory, he added.

The projects that missed their deadline would be given more time for completion as per the government’s decision considering the COVID-19 effect, according to Dhungana.

The contractors have been directed to complete the projects with an expiry of a term within six months.

Two bridges over local Risti and Buduwa streams that started last year have reached their final phase of construction.

Ninety percent of construction works of both bridges have been completed.

Over Rs 2.9 million has been released for the projects, he said. RSS

Publish Date : 15 August 2021 22:31 PM

Sugarcane farmers receive nearly Rs 1.8 billion in pending payments

MAHOTTARI: Sugarcane farmers in Mahottari have received nearly Rs 1.8

Belgium knock USA out of World Cup with commanding 4-1 victory

SEATTLE: Belgium ended the United States’ FIFA World Cup campaign

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of

Paddy plantation declines by 12.62% amid delayed monsoon

KATHMANDU: Paddy transplantation across Nepal has declined by 12.62 percent

“PM focused on domestic priorities first, India and China visits to follow”

KATHMANDU: The government has completed its first 100 days in