Optical fibre backbone network: 22 per cent of works completed in four years



KATHMANDU: The Optical Fibre Backbone Network Expansion Project has become sluggish.

Nepal Telecommunication Authority (NTA) had initiated the project with the goal of expanding the optical fibre network within two years has made only 22 per cent progress in 18 months.

NTA had divided the project of laying optical fibre on 6,331 kilometres of the Mid-hill highway into three sections and given the responsibility of this to three separate companies.

Although the work of laying the optical fibre has been completed in one of the three sections, it has not even been started in remaining two sections.

Nepal Telecom, which had got the responsibility of installing optical fibre in Province no 1, 2 and Bagmati province under the first section, has completed 22.53 per cent of the works so far.

This data is up to December 15. NTA had signed a two-year agreement with Nepal Telecom in September four years back for laying the optical fibre from eastern part of the country up to Gorkha under the first section.

NTA spokesperson Min Prasad Aryal said the Nepal Telecom started the work of laying the optical fibre since May 2019.

According to him, the Telecom has given the responsibility of laying the optical fibre and purchasing goods in three provinces under the first section to five companies.

The data shared by NTA as of December 15 shows that work of laying the optical fibre has been completed in 491 kilometres length in the three provinces.

As per the agreement, fibre has to be installed on 2,179 kilometres in the three provinces. Works yet to start in two sections Meanwhile, works on expanding the optical fibre network have not been started yet in two of the three sections of the project.

The second section includes 2,160 kilometres in 21 districts of the Gandaki and Lumbini provinces. Works have not been started on this section.

The NTA had given the responsibility of laying the optical fibre on this section to the United Telecom. But the works have not started on this section as a case against this is pending at the Supreme Court.

NTA had signed the agreement with UTL for Rs 2.1 billion three years back. It cancelled the agreement with UTL on Baisakh 26, 2076 BS, citing the latter had not started the works within the designated period.

The UTL moved the Supreme Court against this decision and the apex court issued an interim order not to cancel the contract with UTL.

The NTA went for vacating this order and the case is still pending in the court. Similarly, the contract for laying the optical fibre in Karnali and Sudurpaschim provinces has been awarded to Smart Telecom.

The NTA again gave the contract for laying optical fibre on this third section to Nepal Telecom, citing Smart Telecom did not start works in the stipulated time. However, the Nepal Telecom has not started works in this section till date.

RSS

Publish Date : 02 January 2021 06:44 AM

Nepali Congress special convention camp postpones today’s programs after Homanath Dahal’s demise

KATHMANDU: The faction of the Nepali Congress advocating for the

Gandaki govt reaches villages to identify tuberculosis patients

BAGLUNG: The Gandaki provincial government has launched an active campaign

From Kathmandu to Casablanca, a generation under surveillance is rising up

In 2025, youth-led protests erupted everywhere from Morocco to Nepal,

Nepali Congress calls emergency Central Working Committee meeting

KATHMANDU: The Nepali Congress called an emergency meeting of its

Nepali Congress delegates throng Bhrikutimandap ahead of special general convention

KATHMANDU: The Bhrikutimandap area in Kathmandu has begun to witness