Agreement reached on land compensation on Budhigandaki project


10 December 2019  

Time taken to read : 2 Minute


  • A
  • A
  • A

KATHMANDU: The stakeholders concerned have built a uniform voice on sorting out the problems relating to Budhigandaki hydropower project, a national pride project.

A discussion held at the Ministry of Energy on Tuesday forged an agreement to expedite the project activities and work together to resolve disputed issues.

As per the agreement, compensation for the land acquired for the project will range from Rs 50,000 to Rs 700 thousand per ropani. With the distribution of compensation, the stakeholders could meet again for a further decision as per a review of the compensation.

Similarly, Ministry will submit a proposal at the Council of Ministers within two weeks for the discount on depreciation gain tax to the landowners of the project affected areas, said Minister for Energy, Hydropower and Irrigation, Barshaman Pun.

The government has the stand that compensatory gain had to be taxed. The locals receiving compensation were, however, complaining of gain tax.

Publish Date : 10 December 2019 21:15 PM

‘Wrongdoings of some cooperatives defamed those honest ones’

DHANUSHA: Madhesh Province’s Chief Minister Satish Kumar Singh asserted that

Mother killed, son injured in tipper accident in Tanahun

TANAHUN: A woman died, and her son was injured after

Finance Minister pledges payment to construction entrepreneurs

KATHMANDU: Deputy Prime Minister and Minister for Finance Bishnu Paudel

Social Media Bill to strengthen national unity: Communications Minister Gurung

LAMJUNG: Minister for Communications and Information Technology, Prithvi Subba Gurung,

Minister Dahal’s commitment not to back down from the railway project

JHAPA: Minister for Physical Infrastructure and Transport, Devendra Dahal, has