Country’s ‘biggest’ 25 megawatts solar plant links with national transmission line



NUWAKOT: The country’s ‘biggest’ 25 megawatts solar plant based in Nuwakot has been connected to the national transmission line.

Constructed by the Nepal Electricity Authority (NEA), the project was completed three and half years after its foundation stone was laid on April 27, 2018. The project successfully tested power production 15 days ago.

“The power production test took place for consecutive two weeks. It was a success. More than 25 megawatts electricity is being generated due to favorable weather,” said the project Chief Bikash Raghubamshi.

The generated power from the project has connected to the national transmission line through the Devighat hydropower center at Bidur Municipality-6.

The plant that lies in Bidur-6 and 12 was contracted on 17 May, 2017 to Risen Energy, a Chinese company, with the completion target being one year.

However, there had been a delay in the project due to a dilly-dallying in getting the project design passed, it has been said.

As a result, the company started the construction work in 2076 BS. The solar plant is country’s ‘model’ project, claimed the NEA.

Publish Date : 12 September 2022 20:01 PM

WHO to send medicines and health equipment for Bhotekoshi flood victims

KATHMANDU: The World Health Organization (WHO) is preparing to provide

Ncell provides free voice and data services in flood-affected Rasuwa

KATHMANDU: Ncell has announced free voice and data services for three

Four CPN-UML ministers resign in Gandaki Province

POKHARA: Four ministers from the CPN-UML serving in the Gandaki

12 helicopters mobilized for rescue operations in Rasuwa

KATHMANDU: The government has mobilized 12 helicopters to carry out

Rasuwa floods damage six hydropower and transmission facilities

KATHMANDU: The flash floods in Rasuwa have damaged six major hydropower