Rasuwagadhi Hydropower resumes operation after flood repairs



RASUWA: Rasuwagadhi Hydropower Project, damaged by the Lhende Khola flood on July 8, has resumed operation following repair and maintenance works.

According to the Rasuwagadhi Hydropower Centre, 68 megawatts of electricity is currently being fed into the national transmission system after the repair of two out of three turbines, along with restoration of the intake dam and canal. The project has a total installed capacity of 111 megawatts.

Executive Director of Rasuwagadhi Hydropower Company Satya Ram Jyakhwa said that 37 MW was generated in Mangsir, while an additional 31 MW has been added recently after further repairs.

He added that 43 MW of remaining capacity is yet to come online, with full-capacity generation expected during Jestha–Asar (May–June) once cleaning and remaining maintenance works are completed.

The hydropower centre also noted that electricity generation declines during the dry season due to reduced water flow.

The flood had caused significant damage to equipment and infrastructure, resulting in an estimated loss of Rs 3.51 billion, according to the project.

Publish Date : 03 January 2026 12:51 PM

Nepali Congress claims 8 seats in upcoming National Assembly polls

KATHMANDU: Nepali Congress has claimed eight out of 18 seats

NC steps up talks with UML, potential partners ahead of National Assembly elections

KATHMANDU: Nepali Congress has stepped up internal discussions on forming

Provincial chiefs in NC oppose special convention, support regular 15th general convention

KATHMANDU: Internal dissent in the Nepali Congress has reached the

Made in Nepal: Lessons in Business Building from the Land of Everest

KATHMANDU: ‘Made in Nepal’, written by Binod Chaudhary, Nepal’s first

Balen, Kulman absent from RSP unity meeting

KATHMANDU: Balen Shah and Kulman Ghising were absent from the