Underground electrification in Bharatpur reaches 80% completion



CHITWAN: Underground electrification in the Bharatpur Metropolitan City (BMC) area has reached 80 percent completion. The project had aimed to finish the work by mid-March next year, and progress so far remains on track.

The Nepal Electricity Authority’s Pokhara–Bharatpur Distribution System Strengthening Project is implementing the underground electrification along the six-lane road and the bypass in Bharatpur.

According to Project Chief Engineer Ananda Subedi, test transmission has already begun in areas where underground installation has been completed. He said that electricity is currently being supplied through underground lines in about 40 percent of the project area.

“We are moving ahead to complete the work by the end of this month or mid-March,” Subedi said. Ongoing tasks include laying cables, connecting terminations, installing service cables to households, and constructing transformer posts.

He added that the goal is to fully provide underground electricity service within the next three months. However, even after underground transmission begins, the existing utility poles will remain for some time. Although the overhead wires will no longer carry electricity, they will only be removed after assessing whether supply capacity can be maintained during the summer season.

Originally, only the 33 kVA line from the Central Bus Terminal to Gondrang was planned for underground installation. However, Chief Engineer Subedi noted that additional 11 kVA and 400-volt lines are now also being placed underground.

Under the latest agreement, underground electrification has been extended across the core urban area of Bharatpur Metropolitan City, including the installation of the Chanauli line.

The total project cost for underground electrification within Bharatpur Metropolitan City has reached Rs 1.4 billion. Initially, Rs 1.3 billion had been allocated, but an additional Rs 100 million was added as the project scope expanded.

The construction contract was awarded to Tata Projects Limited of India, with work beginning after the agreement was signed in October 2021. The project deadline—originally set for January 20, 2024—has been extended multiple times and now runs until July 2026. The project is being implemented with support from the Asian Development Bank.

Publish Date : 28 November 2025 20:04 PM

Over 400,000 people in Sarlahi to receive anti-elephantiasis medication

SARLAHI: More than 400,000 people across 12 local levels in

President Paudel to pay official visit to Japan from February 1

KATHMANDU: President Ram Chandra Paudel is set to embark on

One shot dead in Siraha

SIRAHA: One person was shot dead in Siraha on Friday

NC Prez Thapa calls for five-year mandate for NC-led govt

DHANUSHA: Nepali Congress (NC) President Gagan Thapa has said that the

Experts warn Nipah virus could enter Nepal from India

KATHMANDU: Following the confirmation of Nipah virus infection in India’s