13 bridges completed on Korala road; three nearing final stage



MUSTANG: A total of 13 bridges have been completed so far under the national pride Beni–Jomsom–Korala road project, which connects Nepal’s southern and northern borders. Three additional bridges are now in their final stages of construction.

The project, launched in FY 2073/74 as a trade corridor linking India and China, confirmed that 13 bridges were completed and handed over to the project office by last year.

Project engineer Bishnu Chapagain said that the contract agreements for three under-construction bridges, including Rupsekhola (Annapurna Rural Municipality-3); Khaharekhola (Thasang-4); and Kagbeni (Waragung Muktikshetra-4), have been terminated due to prolonged delays by contractors and natural disasters.

In the Myagdi section, the Rahughat and Ghattekhola bridges have been completed, while in Mustang, bridges over Letekhola, Setokhola (Thasang-3), Chhaktang Khola (Thasang-2), Marfakhola (Gharpajhong-2), Syangkhola (Gharpajhong-3), Pandakhola, Chhusang Narsingh Khola (Waragung-3), and Charangkhola (Loghekar-1) have also been finished and handed over.

Likewise, the Lomanthang Khola, Kimling Khola, Namdok Khola, and Vermakhola bridges in Upper Mustang have been completed. Chapagain noted that six bridges—including Seto Khola (Thasang-3), Marfakhola (Gharpajhong-2), Narsingh Khola (Baragung-3 Chhusang), Charang Khola (Loghekar Damodarkunda-1), Kimling, and Vermakhola (Lomanthang)—were completed and handed over in FY 2081/82.

The Kaikukhola (Thasang-4), Larjungkhola (Thasang-2), and Ghamikhola (Loghekar Damodarkunda-2) bridges are currently over 80% complete and expected to be handed over within the current fiscal year. Foundation work and slab slopes have been completed, with finishing and approach road construction still ongoing. The project has also built six bailey bridges at Kalipul, Tatopani, Rupse, and Kagbeni Khola in Myagdi, as well as Ghatte Khola (Thasang-2) and Thapakhola (Thasang-1). In total, 19 bridges—both bailey and concrete—have been constructed along the corridor.

Separately, eight concrete bridges have been built between Maludhunga in Parbat and Mustang by the Bridge Sector Office Pokhara and other agencies. These include Damuwa Khola, Lastikhola, Milanchok Khola in Parbat, and Kaligandaki Khola, Begkhola, Tiplyang Khola, and Pokhre Bagar Khola in Myagdi, as well as the Kaligandaki Khola bridge in Jomsom, which was completed with financial assistance from the Indian Embassy.

Publish Date : 07 December 2025 05:36 AM

France, UK consider social media ban for youth as experts debate mental health impact

  KATHMANDU:Countries including France and the United Kingdom are considering

Kulman Ghising to contest from Kathmandu-3

KATHMANDU: Kulman Ghising, chairperson of the Ujyaalo Nepal Party, will

HoR polls: 167 polling stations set up in Parsa

PARSA: The District Security Committee of Parsa has classified 62

Nearly 9 million ballots printed for proportional polls

KATHMANDU: The Election Commission has printed a total of 8,917,000

Pentagon on expansionist plans of China: Beijing’s silence a sign of acquiescence

Beijing’s silence over a Pentagon report that Taiwan, Senkaku Islands