Upper Rahughat Hydropower Project nears completion



MYAGDI: The Upper Rahughat Hydropower Project, with a capacity of 48.5 MW, is in its final stages of construction along the Rahuganga River. The project includes a dam in Ward No. 7, Chimkhola, and a powerhouse in Ward No. 4, Daghnam, connected by a 4,900-meter tunnel currently undergoing lining.

Narottam Karki, an engineer with project promoter Tundi Power Company, stated that construction of the powerhouse, dam, tunnel, and transmission line is nearing completion, with 85% of the physical work finished. The project aims to start electricity production by June 2025.

Tundi Power is also building the Mangale Rahughat Hydropower Project with a capacity of 37.5 MW, featuring a dam in Ward No. 8, Bandi, and a powerhouse in Chimkhola. This project, with a 5,328-meter tunnel, will allow water discharge from Mangale Rahughat’s powerhouse to be collected in the Upper Rahughat dam, explained Tundi Power engineer Prakash Timilsina. Together, both projects are expected to require an investment of over NPR 13 billion.

A 200 kV, 14-kilometer transmission line is also under construction from the Ambang substation in Raghu Ganga Ward No. 3 to Chimkhola to connect the power generated by both projects to the national grid.

Additionally, two other hydropower projects are underway on the Rahughat River: Thulokhola Joint Energy Pvt. Ltd. is developing a 21.3 MW Thulokhola Project, while Thulokhola Hydropower Ltd. is constructing a 22.5 MW Upper Thulokhola Project.

On the same river, Raghu Ganga Hydropower Limited, a subsidiary of the Nepal Electricity Authority, is building the 40 MW Rahughat Hydropower Project.

Publish Date : 31 October 2024 09:26 AM

ICC League 2: Rohit, Ishan power Nepal to six-wicket win over Scotland

KATHMANDU: Nepal national cricket team moved up to fifth place

Acting CJ accuses Supreme Court administration of obstructing justice

KATHMANDU: Acting Chief Justice Sapana Pradhan Malla has ordered the

RSP objects in Parliament to acting CJ’s order on petitions against chief justice recommendation

KATHMANDU: The Rastriya Swatantra Party has objected in the House

Supreme Court staff leave offices after order to register petitions against CJ recommendation

KATHMANDU: Chaos erupted at the Supreme Court on Monday after

NC lawmaker KC questions delay in release of Gen-Z protest report

KATHMANDU: Nepali Congress lawmaker Arjun Narsingh KC has objected to