Gajendra Narayan Singh Hospital construction still incomplete after six years



SAPTARI: The construction of the 300-bed Gajendra Narayan Singh Hospital remains unfinished even after six years.

Originally, the construction company was contracted to complete the project within three and a half years.

The delay in completing the hospital building has adversely affected outpatient and maternity services.

The Ministry of Urban Development signed a construction agreement in January 10, 2019 for a total of Rs 316.20 crore.

Despite receiving three extensions, the project is still not complete. The foundation stone for the building was laid by then Deputy Prime Minister and Minister for Health and Population Upendra Yadav on Poush 26, 2075 BS.

According to the Intensive Urban and Building Construction Project, the construction company has been instructed to finalize the building by next Poush.

Publish Date : 23 November 2024 11:20 AM

Oli and Deuba meet for first time since the Gen-Z protest

KATHMANDU: For the first time since the Gen-Z protest, CPN-UML

Meeting of five parties, EC and security chiefs underway (Photos)

KATHMANDU: A meeting convened by Prime Minister (PM) Sushila Karki

Japan’s Ambassador Maeda meets PM Karki, assures support for timely elections

KATHMANDU: Japan’s Ambassador to Nepal, Toru Maeda, held a courtesy

NPL: Janakpur wins toss, opts to bat

KATHMANDU: Lumbini Lions and Janakpur Bolts are currently facing off

Thapa backs Oli’s continued leadership, calls it a national necessity

KATHMANDU: CPN-UML Vice-Chair Ram Bahadur Thapa has alleged that regressive