Tanahun hydropower project sees above 50 percent progress



DAMAULI: The Tanahun hydropower project, with a capacity of 140 MW, has achieved a 58.1 percent progress.

The work on the hydel is being carried out in three packages, and 52.07 percent of the financial progress has been achieved, said project chief Shyamji Bhandari.

Likewise, 35 percent of progress has been made in the construction of structures including dams under package 1.

Fifty-nine percent progress in the construction of power plants under Package 2 and 73.5 percent of the construction of transmission lines under package-3.

The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.

Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan.

Publish Date : 20 October 2024 14:43 PM

Former minister Pradeep Yadav quits JSP Nepal, joins CPN-UML

KATHMANDU: Former Minister for Drinking Water and leader of the

President Paudel extends Sonam Lhosar greetings

KATHMANDU: President Ram Chandra Paudel has wished that all Nepalis continue

Three Nepali Congress factions hold talks on candidate selection for HoR election

KATHMANDU: Leaders from three factions of the Nepali Congress have

Reminiscing last week: Realignments, retreats, and uncertainty

KATHMANDU: Last week unfolded as one of the most defining

Economic Digest: Nepal’s Business News in a Snap

KATHMANDU: Economic Digest offers a concise yet comprehensive overview of