Tanahun hydropower project sees above 50 percent progress



DAMAULI: The Tanahun hydropower project, with a capacity of 140 MW, has achieved a 58.1 percent progress.

The work on the hydel is being carried out in three packages, and 52.07 percent of the financial progress has been achieved, said project chief Shyamji Bhandari.

Likewise, 35 percent of progress has been made in the construction of structures including dams under package 1.

Fifty-nine percent progress in the construction of power plants under Package 2 and 73.5 percent of the construction of transmission lines under package-3.

The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.

Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan.

Publish Date : 20 October 2024 14:43 PM

RSP maintains lead, wins 100 constituencies so far

KATHMANDU: Vote counting for the House of Representatives (HoR) under

RSP leads PR vote count with over 1 million votes

KATHMANDU: The Rastriya Swatantra Party (RSP) has crossed the one

Foreign currency exchange rates for today

KATHMANDU: Nepal Rastra Bank (NRB) has fixed the foreign currency

Commission to submit Gen-Z protests report to PM Karki today

KATHMANDU: The report on the Gen-Z protests held on September

RSP’s Amaresh defeats Gagan Thapa in Sarlahi-4

SARLAHI: Amaresh Kumar Singh of Rashtriya Swatantra Party (RSP) has