Tanahun hydropower project sees above 50 percent progress


20 October 2024  

Time taken to read : < 1 Minute


  • A
  • A
  • A

DAMAULI: The Tanahun hydropower project, with a capacity of 140 MW, has achieved a 58.1 percent progress.

The work on the hydel is being carried out in three packages, and 52.07 percent of the financial progress has been achieved, said project chief Shyamji Bhandari.

Likewise, 35 percent of progress has been made in the construction of structures including dams under package 1.

Fifty-nine percent progress in the construction of power plants under Package 2 and 73.5 percent of the construction of transmission lines under package-3.

The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.

Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan.

Publish Date : 20 October 2024 14:43 PM

Today’s news in a nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Foreign Minister Dr Rana holds separate meetings with Foreign Ministers of Spain and Slovakia

KATHMANDU: Minister for Foreign Affairs Dr Arzu Rana Deuba held

President, Vice-President worship at Pashupatinath Temple

KATHMANDU: President Ramchandra Paudel and Vice-President Ram Sahay Prasad Yadav

PM Oli meets with players of KP Oli Cup Football Championship

KATHMANDU: Prime Minister KP Sharma Oli met with the players

Nepal’s title hopes shattered as Myanmar clinches Women’s Football Championship

KATHMANDU: Nepal’s long-standing dream of winning an international women’s football