Tanahun hydropower project sees above 50 percent progress



DAMAULI: The Tanahun hydropower project, with a capacity of 140 MW, has achieved a 58.1 percent progress.

The work on the hydel is being carried out in three packages, and 52.07 percent of the financial progress has been achieved, said project chief Shyamji Bhandari.

Likewise, 35 percent of progress has been made in the construction of structures including dams under package 1.

Fifty-nine percent progress in the construction of power plants under Package 2 and 73.5 percent of the construction of transmission lines under package-3.

The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.

Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan.

Publish Date : 20 October 2024 14:43 PM

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of

Heavy rain likely in Bagmati, Gandaki and Lumbini today

KATHMANDU: The monsoon system remains active across Nepal, bringing generally

Breaking the Political Monopoly

Several factors suggest that interest in liberal democratic goals will

Five foreign women arrested over alleged obscene activities in Thamel

KATHMANDU: Nepal Police has arrested five foreign women on charges

Govt marks 100 days with economic reform push

KATHMANDU: The government’s efforts to revive and strengthen the economy