Work of Tanahun hydropower project resumes



DAMAULI: The work of Package I of the 140 MW capacity Tanahun hydropower project under construction in Jhaputar of Rishing Rural Municipality-1 has resumed after 51 days.

The work on the project had been stalled due to a payment dispute.

Head of the project Shyamji Bhandari shared that the work by the joint venture construction company, Songda Kalika, has been re-commenced after the concerned bodies expressed their commitment to provide the due payment for the work through the European Bank.

Under Package I, so far only 35 percent progress has been achieved. Under this package, the construction of two diversion tunnels has been completed to divert the flow of water from the Seti river for the construction of 140 meters high dam of the project.

Publish Date : 08 September 2024 19:22 PM

Traffic enforcement generates Rs 1.33 million in revenue

KATHMANDU: Traffic police took action against 2,042 drivers across the

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of

FIFA World Cup: Portugal edge Croatia 2-1

TORONTO: It took until stoppage time, but Goncalo Ramos rose

Govt advances healthcare reforms in first 100 days

KATHMANDU: The government says it has made progress in improving

Venezuela quake survivor rescued alive after eight days under rubble

CARACUS: A man has been pulled out alive after spending