Work of Tanahun hydropower project resumes



DAMAULI: The work of Package I of the 140 MW capacity Tanahun hydropower project under construction in Jhaputar of Rishing Rural Municipality-1 has resumed after 51 days.

The work on the project had been stalled due to a payment dispute.

Head of the project Shyamji Bhandari shared that the work by the joint venture construction company, Songda Kalika, has been re-commenced after the concerned bodies expressed their commitment to provide the due payment for the work through the European Bank.

Under Package I, so far only 35 percent progress has been achieved. Under this package, the construction of two diversion tunnels has been completed to divert the flow of water from the Seti river for the construction of 140 meters high dam of the project.

Publish Date : 08 September 2024 19:22 PM

Opposition questions PM Shah and RSP’s intentions

  KATHMANDU: Opposition parties have raised serious concerns over Prime

Minister Mahabir Pun makes public first-day decisions

KATHMANDU: Newly appointed Minister for Science, Technology and Innovation Mahabir

Budget discussion to continue in House of Representatives

KATHMANDU: The meeting of the House of Representatives under the

Tehran targets US Gulf bases after American forces launch new strikes on Iran

TEHRAN: Iran has attacked US bases in the Gulf region

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of