Work of Tanahun hydropower project resumes


08 September 2024  

Time taken to read : < 1 Minute


  • A
  • A
  • A

DAMAULI: The work of Package I of the 140 MW capacity Tanahun hydropower project under construction in Jhaputar of Rishing Rural Municipality-1 has resumed after 51 days.

The work on the project had been stalled due to a payment dispute.

Head of the project Shyamji Bhandari shared that the work by the joint venture construction company, Songda Kalika, has been re-commenced after the concerned bodies expressed their commitment to provide the due payment for the work through the European Bank.

Under Package I, so far only 35 percent progress has been achieved. Under this package, the construction of two diversion tunnels has been completed to divert the flow of water from the Seti river for the construction of 140 meters high dam of the project.

Publish Date : 08 September 2024 19:22 PM

Rajendra Lingden: Current government leaning toward authoritarianism

KATHMANDU: Rastriya Prajatantra Party (RPP) Chair Rajendra Lingden criticized the

Expulsion from the party won’t halt my fight against corruption: Bhim Rawal

KATHMANDU: Former CPN-UML leader Bhim Rawal stated that his fight

Nakhhudol bridge awaits maintenance works

LALITPUR: The local residents in the Nakhhu area of Lalitpur

Prime Minister Oli attends RPP’s tea reception

KATHMANDU : Prime Minister KP Sharma Oli has participated in

Rabi released on bail, not declared innocent: Mahat

KATHMANDU:  Spokesperson of the ruling Nepali Congress, Dr. Prakash Sharan