Work of Tanahun hydropower project resumes



DAMAULI: The work of Package I of the 140 MW capacity Tanahun hydropower project under construction in Jhaputar of Rishing Rural Municipality-1 has resumed after 51 days.

The work on the project had been stalled due to a payment dispute.

Head of the project Shyamji Bhandari shared that the work by the joint venture construction company, Songda Kalika, has been re-commenced after the concerned bodies expressed their commitment to provide the due payment for the work through the European Bank.

Under Package I, so far only 35 percent progress has been achieved. Under this package, the construction of two diversion tunnels has been completed to divert the flow of water from the Seti river for the construction of 140 meters high dam of the project.

Publish Date : 08 September 2024 19:22 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Kathmandu Valley dazzles on Laxmi Puja

KATHMANDU: Laxmi Puja, one of the most significant days of

Police arrest nine gamblers

KATHMANDU: Police have arrested nine people for allegedly gambling at

Man arrested with rifle ammunition in Kathmandu

KATHMANDU: Police have arrested a man in possession of a

Police, Army Celebrate Kukur Tihar with special worship and canine skill shows

KATHMANDU: The Nepal Police and Nepali Army marked Kukur Tihar