Work of Tanahun hydropower project resumes



DAMAULI: The work of Package I of the 140 MW capacity Tanahun hydropower project under construction in Jhaputar of Rishing Rural Municipality-1 has resumed after 51 days.

The work on the project had been stalled due to a payment dispute.

Head of the project Shyamji Bhandari shared that the work by the joint venture construction company, Songda Kalika, has been re-commenced after the concerned bodies expressed their commitment to provide the due payment for the work through the European Bank.

Under Package I, so far only 35 percent progress has been achieved. Under this package, the construction of two diversion tunnels has been completed to divert the flow of water from the Seti river for the construction of 140 meters high dam of the project.

Publish Date : 08 September 2024 19:22 PM

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of

NRB fixes foreign currency exchange rates for today

KATHMANDU: Nepal Rastra Bank (NRB) has fixed the foreign exchange

Country to remain generally cloudy today

KATHMANDU: Nepal is currently under the influence of a westerly

Less monsoon rain expected in Hindu Kush-Himalaya region, but risks remain: Study

KATHMANDU: The Hindu Kush-Himalaya (HKH) region is expected to receive

Myagdi’s Raghuganga: Where nature, culture. history converge

BENI: Nestled in the northeastern part of Myagdi district, Raghuganga