Saturday, August 8th, 2026

Work of Tanahun hydropower project resumes



DAMAULI: The work of Package I of the 140 MW capacity Tanahun hydropower project under construction in Jhaputar of Rishing Rural Municipality-1 has resumed after 51 days.

The work on the project had been stalled due to a payment dispute.

Head of the project Shyamji Bhandari shared that the work by the joint venture construction company, Songda Kalika, has been re-commenced after the concerned bodies expressed their commitment to provide the due payment for the work through the European Bank.

Under Package I, so far only 35 percent progress has been achieved. Under this package, the construction of two diversion tunnels has been completed to divert the flow of water from the Seti river for the construction of 140 meters high dam of the project.

Publish Date : 08 September 2024 19:22 PM

Bagmati cleanup campaign collects 4 metric tonnes of non-biodegradable waste

KATHMANDU: Four metric tonnes of non-biodegradable waste were collected during

Manish Jha responds to Balen: The govt. is not alone

KATHMANDU: Rastriya Swatantra Party (RSP) leader Manish Jha has said

Four arrested with 418 Kg of marijuana in Sunsari

SUNSARI: Police have arrested four people with 418 kg of

Father and 10-year-old son embark on Mechi-Mahakali cycling journey

KATHMANDU: A 37-year-old cyclist from Pokhara’s Lakeside has arrived in

Nepal-Oman agreement to promote Nepali products and services in Oman

KATHMANDU: The Exporters Federation of Nepal and the Non-Resident Nepali