Ranke-Rabi-Bhedetar road sees dismal progress in 50 months


27 March 2023  

Time taken to read : < 1 Minute


  • A
  • A
  • A

DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

Today’s news in a nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

People’s representatives should be responsible for public service: Prachanda

DAMAULI: CPN (Maoist Centre) Chairperson and former Prime Minister Pushpa

Minister Yadav directs smooth distribution of Melamchi Water in Kathmandu

KATHMANDU: Minister for Water Supply, Pradip Yadav, has instructed daily

NC to discuss current economic situation and way forward

KATHMANDU: The Nepali Congress is to hold a discussion on

Private medical colleges, govt. hospitals directed to make service fees public

KATHMANDU: The Ministry of Health and Population has asked the