Friday, May 8th, 2026

Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

Narayangadh–Muglin road reopens after landslide clearance

CHITWAN: The Narayangadh–Muglin road section, which was blocked due to

Nepali Army begins high-altitude search and rescue exercise in Mustang

MUSTANG: The Nepali Army has begun a two-day “High Altitude Search

NC strongly objects to Constitutional Council ordinance and appointment process

KATHMANDU: The Nepali Congress (NC) has expressed serious disagreement over

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of

Harka Sampang and Sudan Kirati reach unity agreement, formal announcement today

KATHMANDU: Shram Sanskriti Party Chairperson Harka Sampang and former minister Sudan