Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

NC General Convention: Closed session to end today

KATHMANDU: The closed session of the Nepali Congress’s (NC) 15th

Early weather warnings ease paddy harvesting for Kanchanpur farmers

KANCHANPUR: For years, Nilam Karki had only one way to

Mid-Hill Highway: Three motorable bridges constructed in Kaski

POKHARA: Three concrete motorable bridges have been completed and brought

CPN-UML to hold Standing Committee meeting tomorrow

KATHMANDU: The CPN-UML has convened a meeting of its Standing

China’s Silent Collapse: AI and the Vanishing Future of Its Programmers

The Chinese job market is undergoing a seismic shift, and