Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

Nepal elect to bat first against UAE in ACC Premier Cup final

KATHMANDU: Nepal won the toss and elected to bat first

Process to evict squatters from Pokhara Bus Park area to resume tomorrow

POKHARA: Pokhara Metropolitan City is preparing to resume the process

Foreign currency exchange rates fixed for today

KATHMANDU: Nepal Rastra Bank has fixed the foreign currency exchange

ACC Premier Cup final: Nepal and UAE to clash today

KATHMANDU: Nepal and the United Arab Emirates (UAE) will face

Justice Beyond Borders: Reimagining Law in a Globalised World

The old map of law no longer fits the world