Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

Saptakoshi water flow surges, 21 barrage gates opened

SUNSARI: Water levels in the Saptakoshi River in Koshi Province

Argentina defeat England 2-1 to reach World Cup final

KATHMANDU: Argentina secured their place in the FIFA World Cup

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

RSP to inform public about government’s achievements through lawmakers

KATHMANDU: The Rastriya Swatantra Party (RSP) has announced plans to

Meta sued over alleged AI-driven layoffs targeting employees on protected leave

SAN FRANCISCO: Twenty-six former Meta employees have filed a lawsuit