Madhya Bhotekoshi Hydro project near completion



KATHMANDU: The 102-megawatts-capacity Madhya Bhotekoshi Hydropower Project has neared its completion.

Developed by the Chilime Hydropower Company, a subsidiary of the Nepal Electricity Authority, the run-of-the-river project is under construction at a speedy pace with the aim of completing it in next four months, said the project officer, adding that so far, 95 percent construction work has been completed.

Almost all construction work has been over, while remaining work of building walls and other security related infrastructures remains, it has been said. Works like concrete lining in the tunnel, and fitting equipment at turbines, generators and control rooms are underway.

It may be noted that the project got a delay due to various problems. Started in 2013 with the completion deadline being 2016, it missed multiple completion deadlines in between.

The project cost was estimated to be over Rs 12.28 billion excluding interest since the time when there was a loan agreement reached with the Employees’ Provident Fund. It has now increased to Rs 15.3 billion excluding interest of the project’s periodic projected cost.

It is expected to produce over 542 million units of electricity annually, generating over Rs 2.8 billion a year.

Publish Date : 10 March 2023 18:48 PM

13 arrested from various locations with drugs

KATHMANDU: Police have arrested 13 individuals from different parts of

Harka Sampang opposes personal secretary allowance for lawmakers

KATHMANDU: Harka Raj Rai, the Chairman of the Shram Sanskriti

Armed Police Force tightens border security in Jhapa to curb revenue leakage

KAKARBHITTA: The Armed Police Force (APF) has intensified surveillance at

Two youths die in road accident in Kailali

KAILALI: Two people have died after a speeding vehicle hit

Economic Digest: Nepal’s Business News in a Snap

KATHMANDU: Economic Digest offers a concise yet comprehensive overview of