Lockdown hits construction of 9 hydroelectricity projects in Lamjung



LAMJUNG: The nationwide lockdown enforced to stem the spread of coronavirus has affected nine hydroelectricity projects in Lamjung district.

Managers of the nine under construction hydel-projects with 202-megawatt aggregate capacity said construction works of the projects were hit hard for lack of supply of construction materials and sufficient number of workers.

The government after two weeks into lockdown had urged the large construction projects to continue works. But, the works have failed to resume in the lack of necessary resources at the local level.

The managers viewed they faced problems as construction materials including cement, sand, steel bars needed to be brought in from other districts.

Publish Date : 24 May 2020 16:03 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Israel confirms Hamas armed wing chief killed in Gaza strike

JERUSALEM, (AFP): Hamas’s armed wing chief Ezzedine Al-Haddad, described by

Government assures regular supply of sugar and essential goods

KATHMANDU: The government has said it is fully committed to

Missing trekker found dead near Mardi viewpoint

KASKI: A tourist who went missing during a trek to

Congress in weakest phase in its history: former acting president Khadka

SURKHET: Nepali Congress is currently in one of the most