Shortage of stone takes toll on Mahakali bridge construction


16 March 2020  

Time taken to read : 2 Minute


  • A
  • A
  • A

BHIMDUTTANAGAR: The construction of a four-lane bridge over the Mahakali River at Bhimdutta municipality-12, Odali has been adversely affected due to the shortage of stone and soil.

It requires some 600,000 cube meter soil for the construction of the pond dam on both sides of the bridge. However, the problem has arisen when the clause of stone and soil was not part of the contract agreement.

The plan is to construct a 5,200-meter dam along both sides of the bridge – considered to be the commercial checkpoint of the far-western region.

Engineer Kishor Raj Pandey, who has been involved in the construction of the bridge, informed that the contract has included the construction of two dams, each with a length of 2,600 meters on both sides of the bridge.

He said that the construction of the dam has not been initiated as the process for variation for soil has yet to be completed.

The dam construction requires around 150,000 large-size stones, which has not been arranged yet.

Publish Date : 16 March 2020 11:42 AM

Today’s news in a nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Govt forms High-Level Economic Sector Reform Recommendation Commission

KATHMANDU: The government has formed a High-Level Economic Sector Reform

Melamchi drinking water distribution begins in Kathmandu

KATHMANDU: The distribution of Melamchi water has commenced in the

Govt to bring 20 bailey bridges from India

CHAUTARA: The government has planned to bring 20 bailey bridges

Rita Dhital appointed as Nepali Ambassador to Pakistan

KATHMANDU: Rita Dhital has been appointed as the Nepalese Ambassador