59 pc work of Pokhara Regional Int’l Airport completed


14 June 2020  

Time taken to read : < 1 Minute


  • A
  • A
  • A

POKHARA: The construction work of Pokhara Regional International Airport has been completed by 59 percent.

However, the financial progress of the project of national pride is only 45 percent.

As many as 250 Chinese and 100 Nepali workers are working daily in the project which has not been stopped for a single day during the lockdown.

Construction of 14 buildings including terminal, tower, immigration, customs, hangar, cargo, administrative, fire control, quarantines and rescue is underway, media reports said on Sunday.

Publish Date : 14 June 2020 19:13 PM

Economic Digest: Nepal’s Business News in a Snap

KATHMANDU: Economic Digest offers a concise yet comprehensive overview of

CIB hands over Rabi to Kaski Police amid protests

POKHARA: The Central Investigation Bureau (CIB) of the Nepal Police

 Today’s weather forecast: Partly cloudy across the country, light rain expected in hill areas

KATHMANDU: The Department of Hydrology and Meteorology has reported that

Today’s foreign currency exchange rates

KATHMANDU: Most foreign currencies have appreciated, including pound sterling, Australian

Today’s news in a nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of