59 pc work of Pokhara Regional Int’l Airport completed



POKHARA: The construction work of Pokhara Regional International Airport has been completed by 59 percent.

However, the financial progress of the project of national pride is only 45 percent.

As many as 250 Chinese and 100 Nepali workers are working daily in the project which has not been stopped for a single day during the lockdown.

Construction of 14 buildings including terminal, tower, immigration, customs, hangar, cargo, administrative, fire control, quarantines and rescue is underway, media reports said on Sunday.

Publish Date : 14 June 2020 19:13 PM

Koshi CM refuses to step down without formal UML decision

BIRATNAGAR: Koshi Province Chief Minister Hikmat Karki has reportedly refused

Forest and environmental conservation must be prioritised: Agriculture Minister

JANAKPURDHAM: Minister for Agriculture, Forests and Environment Gita Chaudhary has

Probe committee formed over Narayani Hospital death

BIRGUNJ: A five-member committee has been formed to investigate the

Lumbini Nepali Congress ministers resign as coalition shift looms

BUTWAL: Nepali Congress (NC) ministers in the Lumbini Provincial Government

UML-NCP alliance sparks dissent among party ranks

KATHMANDU: The UML-NCP (Nepali Communist Party )provincial government coalition, announced