Only 27 per cent of Tarkeshwor housing reconstruction completed



KATHMANDU: Even after four years since the devastating earthquake of April 2015, only 27 per cent of private housing reconstruction of Tarakeshwor municipality has been completed.

Senior engineer at the municipality Shashi Gurung said that lack of clear policy in demolition and reconstruction of the damaged houses built on Guthi land, lack of budget and land ownership certificates have caused the delay in reconstruction.

Among the total 6,174 damages houses, only 1,652 beneficiaries of the grant have reconstructed their houses, according to the municipality.

Around 5,062 beneficiaries have so far received the first tranche of the housing grant, while 2,085 have received the second installments, according to Gurung.

Publish Date : 28 August 2019 17:52 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Woman arrested for defrauding victims of Rs 3.85 million with false promise of jobs in US

KATHMANDU: Police have arrested a woman on charges of defrauding

Jewellery shop owner arrested for allegedly staging theft to claim insurance

KATHMANDU: Police have arrested a jewellery shop owner and an

Discussions begin on annual estimates of revenue and expenditure for upcoming fiscal year

KATHMANDU: General discussions have begun in the House of Representatives

Protesters block road to Mexico City’s World Cup stadium ahead of opening match

MEXICO CITY: A major avenue leading to Azteca Stadium was