Irregular supply of electricity affects Karnali districts



JAJARKOT: Four districts in the far-west have been deprived of regular power supply due to the delayed construction of the 132-KV transmission substation.

The construction has been delayed due to hassles relating to environment impact assessment (EIA) and lack of clarity on cost estimate, authorities said.

Similarly, the Kohalpur-Jajarkot 33-kv transmission line has been facing problems in power supply due to the placement of a substation on a longer distance than of the required.

Likewise, power supply to Dailekh, Surkhet, and Rukum west has also been affected due to the same reason.

Publish Date : 21 April 2019 15:08 PM

NOC begins distributing half-filled LPG cylinders to manage demand surge

KATHMANDU: The Nepal Oil Corporation has started distributing half-filled cooking

KMC removes bus advertisement materials after contract expiry

KATHMANDU: Kathmandu Metropolitan City has begun removing advertisement materials from

NC to submit names of 20 PR MPs to EC tomorrow

KATHMANDU: Nepali Congress (NC) is set to submit the names

Students stage protest in Kathmandu demanding justice for Inisha BK

KATHMANDU: Students staged a protest in Kathmandu on Friday, demanding

RSP holds internal discussions to finalize proportional representation nominees

KATHMANDU: The Rastriya Swatantra Party is holding internal discussions to