Construction works of Mid-Hill Highway accelerated



KATHMANDU: The construction works of the Mid-Hill Highway (MHH) have been expedited so as to complete the national pride project within the stipulated time.

The construction of Highway had begun in the 2007/8 fiscal year and is aimed to be completed by 2021/22.

Altogether 344-km of 1,776-km Highway has been blacktopped while the process for the contract has been forwarded to do blacktopping and opening new tracks for the Highway.

MHH Project Directorate Chief Deepak KC shared that 581-km of the road under the MHH has been completed so far. Altogether 68 bridges have been built along the Highway and 24 more are under construction, according to KC.

A new track for the road measuring 879 km has been opened while the roads built already will be upgraded on part with the standard of the MHH, informed KC.

The MHH was enlisted in the national pride project since 2012/13.

Publish Date : 15 November 2019 21:49 PM

No increase in Internet tariffs, NTA warns of action against overcharging

KATHMANDU: The Nepal Telecommunications Authority (NTA) has clarified that internet

Continuous rainfall blocks several highways

KATHMANDU: Continuous rainfall has disrupted road connectivity in various parts

31 arrested in drug-related cases

KATHMANDU: Police have arrested 31 people from various parts of

Landslide blocks BP Highway, rain hampers clearance

KAVRE: The BP Highway has been completely blocked by a

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of