Power supply to be disrupted for 12 hours in eastern Nepal on Saturday



KATHMANDU: Electricity supply will remain disrupted for 12 hours in Jhapa, Ilam, Panchthar and Taplejung districts, as well as Urlabari, Pathari and surrounding areas of Morang, on Saturday.

According to the Nepal Electricity Authority (NEA), power supply will be interrupted from 4:00 am to 4:00 pm due to maintenance and testing works on the Duhabi–Damak 132 kV transmission line.

The disruption is necessary to install a dead-end tower between tower numbers 68 and 69 at Keroun, carry out transmission line maintenance and conduct substation testing, officials said.

Project Chief Darshan Rai Yadav said the substation operation would help ensure a more reliable, quality and regular electricity supply in Morang areas including Belbari, Rangeli, Urlabari and Pathari.

The NEA has requested consumers in the affected areas to take necessary precautions during the scheduled outage.

Publish Date : 07 August 2026 17:34 PM

Voting for new Nepali Congress leadership to begin at 10 am Thursday

KATHMANDU: Voting to elect the new Central Working Committee of

Gagan Thapa’s ‘National Renaissance and Prosperity’ proposal approved

KATHMANDU: Various proposals and reports have been approved at the

NC president gets greater authority to nominate 61 central members, four joint general secretaries

KATHMANDU: The Nepali Congress statute grants the party president the

Angdembe warns algorithm-driven popularity could push Nepal toward a Ukraine-like situation

KATHMANDU: Nepali Congress parliamentary party leader Bhishma Raj Angdembe has

Efforts underway to make Gagan Thapa Nepali Congress president unopposed

KATHMANDU: Efforts are underway to make Gagan Kumar Thapa the