Completion of Kohalpur-Surkhet transmission line on track



KATHMANDU: The construction of the Kohalpur-Surkhet 132 kV transmission line, which was supposed to be completed by July 7, 2021, is still pending.

Despite an agreement being signed with Indian company RS Infraproject in 2019 for a project costing Rs 700 million, the transmission line has not yet reached Surkhet.

The project faced delays due to land acquisition issues and tree felling in the Banke and Bardiya National Park areas.

The situation was resolved, but the work came to a standstill when locals of Gavar, Baniyabhar, and Baijanath Rural Municipality-1 in Banke obstructed the construction for over 42 months.

In response to the obstruction, locals filed a writ petition in High Court in Nepalgunj, but the court dismissed the petition, ruling that the construction should proceed with the necessary compensation to the affected citizens. As a result, nine towers—six in Gavar and three in Baniyabhar—remain incomplete.

Project Chief Rabi Chaudhary said while compensation for landowners in Gavar has been settled, issues persist in Baniyabhar, where compensation has been agreed upon but not yet fully executed.

Banke Chief District Officer Khagendra Rijal confirmed that the issue is near resolution, with the administration ready to resolve any further obstacles.

The price of the land where the towers are being constructed has been fixed between Rs 2.5 million to Rs 3.2 million, and the transmission line spans 52 kilometers, with 161 towers planned between Kohalpur and Surkhet.

As of now, construction is complete for a 32-km stretch in the Surkhet section, while work continues in other areas, including Harre-Chinchu-Subbakuna and Kohalpur-Chisapani.

The construction has faced challenges due to the fourteen-km stretch within the Banke and Bardiya National Parks.

After receiving permission to fell trees, the project is progressing with tree cutting and tower construction. The target is to complete the tree felling work within the next two months.

According to Project Chief Chaudhary, 80 percent of the physical progress of the project has been completed, and the aim is to begin electricity transmission to the Birendranagar substation by May 2025.

The project will resolve ongoing power irregularities and voltage problems in Surkhet and Karnali districts, which are currently being powered by outdated 33 kV transmission lines.

Publish Date : 31 December 2024 11:40 AM

Department of Passports resumes full-capacity service

KATHMANDU: The Department of Passports has announced that it will

Early morning chill persists in Kathmandu Valley

KATHMANDU: The Kathmandu Valley recorded the same minimum temperature on

NC holding Central Work Execution Committee meeting today

KATHMANDU: The Nepali Congress (NC) is holding a meeting of

Election 71 days away: Parties intensify PR list preparations

KATHMANDU: With 71 days remaining until the election of members

Three Shocks that Shook the World in 2025

This was the year that the remaining pillars of the