Tanahun hydropower project sees above 50 percent progress



DAMAULI: The Tanahun hydropower project, with a capacity of 140 MW, has achieved a 58.1 percent progress.

The work on the hydel is being carried out in three packages, and 52.07 percent of the financial progress has been achieved, said project chief Shyamji Bhandari.

Likewise, 35 percent of progress has been made in the construction of structures including dams under package 1.

Fifty-nine percent progress in the construction of power plants under Package 2 and 73.5 percent of the construction of transmission lines under package-3.

The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.

Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan.

Publish Date : 20 October 2024 14:43 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Petroleum imports generate over Rs 60.38 billion in revenue in nine months

KATHMANDU: The government has collected Rs 60.38 billion in revenue

Woman dies after lightning strike in Parbat

PARBAT: A woman has died after being struck by lightning

128 arrested in two-day drug crackdown ‘sweep operation’ in Jhapa

JHAPA: Police have arrested 128 individuals in a two-day sweep

Heavy rainfall recorded in multiple districts, more rain likely

KATHMANDU: Several districts across Nepal witnessed heavy rainfall as weather