Tanahun hydropower project sees above 50 percent progress


20 October 2024  

Time taken to read : < 1 Minute


  • A
  • A
  • A

DAMAULI: The Tanahun hydropower project, with a capacity of 140 MW, has achieved a 58.1 percent progress.

The work on the hydel is being carried out in three packages, and 52.07 percent of the financial progress has been achieved, said project chief Shyamji Bhandari.

Likewise, 35 percent of progress has been made in the construction of structures including dams under package 1.

Fifty-nine percent progress in the construction of power plants under Package 2 and 73.5 percent of the construction of transmission lines under package-3.

The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.

Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan.

Publish Date : 20 October 2024 14:43 PM

Today’s news in a nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Over 1,700 new industries registered in Karnali

SURKHET: In the current fiscal year, 1,795 small industries have

Government decides on free treatment service to needy burn patients

KATHMANDU: The government has decided to treat burns free of

Ministry of Urban Development makes public 100 days’ progress

KATHMANDU: Deputy Prime Minister and Minister for Urban Development Prakash

CPN-UML seeks clarification from leaders over statements on party’s land donation

KATHMANDU: CPN-UML has decided to seek clarification from those leaders