Tanahun hydropower project sees above 50 percent progress



DAMAULI: The Tanahun hydropower project, with a capacity of 140 MW, has achieved a 58.1 percent progress.

The work on the hydel is being carried out in three packages, and 52.07 percent of the financial progress has been achieved, said project chief Shyamji Bhandari.

Likewise, 35 percent of progress has been made in the construction of structures including dams under package 1.

Fifty-nine percent progress in the construction of power plants under Package 2 and 73.5 percent of the construction of transmission lines under package-3.

The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.

Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan.

Publish Date : 20 October 2024 14:43 PM

Former Speaker Ghimire loses Jhapa-2 seat to Indira Rana

JHAPA: Former Speaker Devraj Ghimire has been defeated in the

UML’s Suhang Nembang secures second win in Ilam-2

ILAM: CPN-UML candidate Suhang Nembang has been elected from Ilam

Kshitij Thebe of CPN-UML wins Taplejung seat

KATHMANDU: Kshitij Thebe of the CPN-UML has won the House

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

RSP’s Nisha Dangi wins Jhapa-1

JHAPA: Rastriya Swatantra Party’s Nisha Dangi has won the House