Tanahun hydropower project sees above 50 percent progress


20 October 2024  

Time taken to read : < 1 Minute


  • A
  • A
  • A

DAMAULI: The Tanahun hydropower project, with a capacity of 140 MW, has achieved a 58.1 percent progress.

The work on the hydel is being carried out in three packages, and 52.07 percent of the financial progress has been achieved, said project chief Shyamji Bhandari.

Likewise, 35 percent of progress has been made in the construction of structures including dams under package 1.

Fifty-nine percent progress in the construction of power plants under Package 2 and 73.5 percent of the construction of transmission lines under package-3.

The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.

Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan.

Publish Date : 20 October 2024 14:43 PM

Gajendra Narayan Singh Hospital construction still incomplete after six years

SAPTARI: The construction of the 300-bed Gajendra Narayan Singh Hospital

Construction of 135 MW Manang Marsyangdi HP starts

KATHMANDU: Financial closure for the 135 MW Manang Marsyangdi Hydropower

Calls to revoke China’s trade status widen in Washington

WASHINGTON DC: Influential members of Congress, including the senator poised

Power from Sanjen Hydro Project connected to national grid

KATHMANDU: The power produced by the Sanjen Hydropower Project has

Economic Digest: Nepal’s Business News in a Snap

KATHMANDU: Economic Digest offers a concise yet comprehensive overview of