Narayangarh-Butwal road section: 18-km blacktopped in eastern section



NAWALPUR: The task of blacktopping in the eastern section of Narayangarh-Butwal road stretch along the East-West Highway has gained momentum.

Blacktopping has completed in 18.5 kilometers out of 65 kilometers from Gaidakot to Daunne in the eastern section.

According to contract manager of the China State Construction Engineering Corporation Limited Rakesh Jha, one side blacktopping with sub-base, construction of large bridges and walls along the road stretch and rivulet banks are being carried out.

He informed that road expansion works are being carried out in a way to complete one-side blacktopping in 42-km section in next two months.

He shared that emphasis has been laid on expediting the construction of big structures along the road.

“Four out of five kilometers in Daunne has been expanded by cutting the mountain area”, he said, adding, “Works are being expedited to complete soil cutting in remaining one kilometer section in next one month”.

Now the road expansion has gained momentum from Bhedabari to Jharahi khola of Gandakot as well as in Rajahar of Devchuli, Danda Bazaar of Kawaswoti and Kawaswoti Bazaar area.

Publish Date : 27 December 2023 12:54 PM

Three unlicensed guns found in forest; woman arrested with drugs

BAGLUNG: A police patrol team recovered three unlicensed guns from

Seven bodies recovered from Upper Trishuli-1 hydropower project

RASUWA: Seven bodies have been recovered from the flood-damaged Upper

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of

Nepal elect to bat first against UAE in ACC Premier Cup final

KATHMANDU: Nepal won the toss and elected to bat first

Process to evict squatters from Pokhara Bus Park area to resume tomorrow

POKHARA: Pokhara Metropolitan City is preparing to resume the process