Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

Indian Ambassador meets Foreign Minister Khanal, discusses bilateral cooperation

KATHMANDU: Indian Ambassador to Nepal Naveen Srivastava paid a courtesy

Expressway system to be used for courier goods sent and received via post

KATHMANDU: An expressway system will now be used for the

Gold price drops by Rs 2,600 per tola

KATHMANDU: Gold prices declined on Monday, according to the Federation

Eight construction companies blacklisted

KATHMANDU: The Public Procurement Monitoring Office under the Prime Minister’s

RSP yet to decide deputy speaker as opposition parties stake claim

KATHMANDU: The Rastriya Swatantra Party (RSP) has yet to finalize