Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

Rain expected in several parts of country today

KATHMANDU: The Weather Forecasting Division has forecast the possibility of

Besisahar-Chame road to remain closed throughout today

LAMJUNG: The Besisahar-Chame road connecting Lamjung and Manang will remain

Three unlicensed guns found in forest; woman arrested with drugs

BAGLUNG: A police patrol team recovered three unlicensed guns from

Seven bodies recovered from Upper Trishuli-1 hydropower project

RASUWA: Seven bodies have been recovered from the flood-damaged Upper

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of