Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

Kulman Ghising-led Ujyalo Nepal unveils election manifesto

KATHMANDU: The Ujyala Nepal Party, chaired by Kulman Ghising, unveiled

ICC World Cup: Nepal suffers heavy defeat against West Indies

KATHMANDU: Nepal suffered a heavy 9-wicket defeat against the West

Atmosphere of confidence not ready for polls: Oli

JHAPA: CPN-UML Chairman KP Sharma Oli, arriving in Jhapa on

Man dies after scooter hits pedestrian in Gaindakot

NAWALPUR: A pedestrian died after being struck by a scooter

ICC T20: Nepal set 134-run target for West Indies

KATHMANDU: With a fighting half-century from Dipendra Singh Airee, Nepal