Eight years on, bridge construction sees only 20 percent progress



DOTI: Eight years into construction, a bridge over the Seti River in Shikhar Municipality-10 in Doti district has witnessed only 20 percent physical progress.

The Federal Road Supervision and Monitoring Office, Road Division Office, Kulpate had signed a contract with the Pushpa-Rajendra JV Construction Company in 2014 to complete the construction works by the end of 2017.

Negligence on the part of the contractor has been blamed for the delay. The agreement has been extended four times in between. The 320-meter long bridge linking the KI Singh Highway costs Rs 262 million, including value-added tax. So far, Rs 32 million has been released for the project, said the Road Division Office.

The contractor has cited COVID-19 and lack of workforce for the delay, said engineer Yogendra Bahadur Adhikari, also an information officer of the Road Division Office.

Problems in the project foundation have caused the delay, said the contractor.

Publish Date : 12 February 2022 21:06 PM

ANFA Women’s League kicks off in Kathmandu from Wednesday

  KATHMANDU: The All Nepal Football Association (ANFA) is set

UML’s Shankar Pokharel says RSP rise driven by populism, opportunism

KATHMANDU: General Secretary of the CPN-UML, Shankar Pokharel, has said

Nepal faces no major gas or fuel shortages, officials confirm

KATHMANDU: More than two weeks after the United States and

SC ruling ends dual allowance for 11 Nepal Academy lifetime members

KATHMANDU: Eleven lifetime members of the Nepal Academy will no

RSP lawmaker Ashika Tamang’s directive on local tax sparks controversy

KATHMANDU: A directive issued by Ashika Tamang, a lawmaker from