KATHMANDU: The expansion of the Suryabinayak-Dhulikhel section of the Kathmandu-Araniko Highway into a six-lane road remains incomplete even after four years of construction, with progress falling short of expectations in both project sections.
The road expansion project, divided into the Suryabinayak-Sanga and Sanga-Dhulikhel sections, was initiated in Januaru 2022. However, construction has yet to be completed despite the passage of several years.
A contract worth approximately Rs 3.8893 billion was signed for the expansion of the 7.5-kilometre Suryabinayak-Sanga section. Construction progress on this stretch has reached around 55 percent.
Similarly, the 8.4-kilometre Sanga-Dhulikhel section is being expanded under a contract worth approximately Rs 4.564 billion. Physical progress on this section has reached about 77 percent.
Under the original agreements, construction of both sections is scheduled to be completed by March this year.
Work on the project was delayed by a dispute over road standards in the Banepa Bazaar area. Construction activities resumed after the dispute was resolved last Kartik, according to the project details.
Meanwhile, the ongoing construction has created significant difficulties for commuters and motorists using the busy Araniko Highway. Dust, traffic congestion and frequent disruptions have made travel increasingly uncomfortable, particularly along sections where construction work is underway.
Although construction has resumed, the slow pace of progress and continued traffic disruptions have raised concerns among road users awaiting the completion of the long-delayed project.
Once completed, the expanded highway is expected to improve traffic flow, ease congestion and enhance connectivity between Kathmandu Valley and Kavrepalanchok.