Eleven kilometers of Nagdhunga-Malekhu road blacktopped



CHITWAN: The 11-kilometer Nagdhunga-Malekhu section of the Prithvi Highway has been blacktopped, with eight kilometers completed last year and an additional three kilometers finished this year.

According to Bijay Darai, Project Engineer of the Nagdhunga-Muglin Road Project, 40 percent of the third phase, including Kurintar, Fisling, Charaudi, and parts of Bishaltar, has been blacktopped so far.

Blacktopping work is ongoing in Bandre in Dhading, while bases and subbases have been laid in the Fisling and Jawang Khola areas. Of the six bridges in this section, construction is underway at Hugdi and Charaudi. Darai said the project is committed to ensuring there is no shortage of construction materials.

Although materials have been brought from Charaudi, Benighat, and Ichchakamana in Dhading, he expressed concern that supply shortages could persist for some time. The 38-kilometer road section is being upgraded with a World Bank loan of Rs 4.8059 billion.

Publish Date : 15 February 2026 16:03 PM

Major agenda is fulfillment of public aspiration: NC President

SARLAHI: Nepali Congress (NC) President Gagan Kumar Thapa has said

Kulman Ghising-led party prioritizes health sector in manifesto

KATHMANDU: The Ujyalo Nepal Party, led by Kulman Ghising, has

Voter education kicks off at all local levels in Kathmandu

KATHMANDU: A voter education programme has been launched in all

EC issues 64-point directive for candidates

KATHMANDU: The Election Commission Nepal has issued a 64-point directive

Rabi Lamichhane unveils ‘Citizen Contract’: Not talk, but action; not speeches, but results

KATHMANDU: Rastriya Swatantra Party (RSP) Chair Rabi Lamichhane on Sunday