Eleven kilometers of Nagdhunga-Malekhu road blacktopped



CHITWAN: The 11-kilometer Nagdhunga-Malekhu section of the Prithvi Highway has been blacktopped, with eight kilometers completed last year and an additional three kilometers finished this year.

According to Bijay Darai, Project Engineer of the Nagdhunga-Muglin Road Project, 40 percent of the third phase, including Kurintar, Fisling, Charaudi, and parts of Bishaltar, has been blacktopped so far.

Blacktopping work is ongoing in Bandre in Dhading, while bases and subbases have been laid in the Fisling and Jawang Khola areas. Of the six bridges in this section, construction is underway at Hugdi and Charaudi. Darai said the project is committed to ensuring there is no shortage of construction materials.

Although materials have been brought from Charaudi, Benighat, and Ichchakamana in Dhading, he expressed concern that supply shortages could persist for some time. The 38-kilometer road section is being upgraded with a World Bank loan of Rs 4.8059 billion.

Publish Date : 15 February 2026 16:03 PM

Hydropower project swept away just days before power generation, 60 workers missing

KATHMANDU: The under-construction Langtang Khola Hydropower Project in Rasuwa, which

China’s weather agency links Nepal’s flash floods to heavy rain in Tibet, different explanations under study

KATHMANDU: China’s government weather agency has attributed the flash floods

Landslide across China border linked to devastating Bhote Koshi flood

KATHMANDU: A preliminary study by the National Disaster Risk Reduction

25 injured in Rasuwa floods brought to Kathmandu for treatment

KATHMANDU: Twenty-five people injured in the flooding of the Bhotekoshi

Modi calls PM Balen, assures India’s full support for flood relief

KATHMANDU: Indian Prime Minister Narendra Modi has called Nepal’s Prime