Eleven kilometers of Nagdhunga-Malekhu road blacktopped



CHITWAN: The 11-kilometer Nagdhunga-Malekhu section of the Prithvi Highway has been blacktopped, with eight kilometers completed last year and an additional three kilometers finished this year.

According to Bijay Darai, Project Engineer of the Nagdhunga-Muglin Road Project, 40 percent of the third phase, including Kurintar, Fisling, Charaudi, and parts of Bishaltar, has been blacktopped so far.

Blacktopping work is ongoing in Bandre in Dhading, while bases and subbases have been laid in the Fisling and Jawang Khola areas. Of the six bridges in this section, construction is underway at Hugdi and Charaudi. Darai said the project is committed to ensuring there is no shortage of construction materials.

Although materials have been brought from Charaudi, Benighat, and Ichchakamana in Dhading, he expressed concern that supply shortages could persist for some time. The 38-kilometer road section is being upgraded with a World Bank loan of Rs 4.8059 billion.

Publish Date : 15 February 2026 16:03 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Around 60 lawyers detained near India’s Supreme Court

KATHMANDU: Police in New Delhi have detained around 60 lawyers

Nepali Congress begins vote counting for vice president and general secretary posts

KATHMANDU: Vote counting for the vice president and general secretary

Session of Koshi Provincial Assembly prorogued

BIRATNAGAR: The Office of the Koshi Province Chief has announced

Ministry forms committee to review government software and hardware purchases

KATHMANDU: The Ministry of Land Management, Cooperatives and Poverty Alleviation