Eleven kilometers of Nagdhunga-Malekhu road blacktopped



CHITWAN: The 11-kilometer Nagdhunga-Malekhu section of the Prithvi Highway has been blacktopped, with eight kilometers completed last year and an additional three kilometers finished this year.

According to Bijay Darai, Project Engineer of the Nagdhunga-Muglin Road Project, 40 percent of the third phase, including Kurintar, Fisling, Charaudi, and parts of Bishaltar, has been blacktopped so far.

Blacktopping work is ongoing in Bandre in Dhading, while bases and subbases have been laid in the Fisling and Jawang Khola areas. Of the six bridges in this section, construction is underway at Hugdi and Charaudi. Darai said the project is committed to ensuring there is no shortage of construction materials.

Although materials have been brought from Charaudi, Benighat, and Ichchakamana in Dhading, he expressed concern that supply shortages could persist for some time. The 38-kilometer road section is being upgraded with a World Bank loan of Rs 4.8059 billion.

Publish Date : 15 February 2026 16:03 PM

25 injured in Rasuwa floods brought to Kathmandu for treatment

KATHMANDU: Twenty-five people injured in the flooding of the Bhotekoshi

Modi calls PM Balen, assures India’s full support for flood relief

KATHMANDU: Indian Prime Minister Narendra Modi has called Nepal’s Prime

Rescue efforts continue in flood-hit Nuwakot as families search for loved ones

KATHMANDU: Security personnel, including the Nepali Army, have continued aerial

India, China and World Bank step up support for flood-hit Nepal

KATHMANDU: India, China and the World Bank have stepped up

Disaster Authority urges stranded people to signal rescue teams with smoke

KATHMANDU: The National Disaster Risk Reduction and Management Authority (NDRRMA)