Upper Myagdi-1 Hydropower Project achieves tunnel breakthrough



MYAGDI: The 35.5 MW Upper Myagdi-1 Hydropower Project has achieved a major milestone with the breakthrough of a section of its headrace tunnel from the adit toward the dam site.

Promoted by Myagdi Hydropower Limited, the project connected the tunnel excavated from the adit site at Chhahari in Dhaulagiri Rural Municipality-4 to the under-construction powerhouse at Bharwang in Malika Rural Municipality-7 on Wednesday.

Project Chief Jyoti Kumar KC said a 2,506.39-meter section of the tunnel connecting the adit site to the dam has been excavated and broken through. Of the total 3,283.32-meter tunnel planned from Chhahari to the dam site in Dhaulagiri Rural Municipality-4, 1,973 meters have been completed so far, KC said.

“Work is progressing with the aim of completing the remaining section of the tunnel within the next few months,” he said. According to KC, overall physical progress of the project has reached 56 percent, and construction is expected to be completed within the next year.

Publish Date : 10 September 2026 08:15 AM

Bhotekoshi flood: Details of 2,294 missing persons made public

KATHMANDU: The National Disaster Risk Reduction and Management Authority (NDRRMA)

Foreign Minister Khanal leaves for Türkiye to lead Nepali delegation to COP31

KATHMANDU: Minister for Foreign Affairs Shisir Khanal departed for Antalya,

Parliamentary Hearing Committee endorses four nominees for Supreme Court judges

KATHMANDU: The Parliamentary Hearing Committee of the Federal Parliament has

Power demand expected to reach 1,700 MW on Laxmi Puja: NEA

KATHMANDU: Peak electricity demand in Nepal is expected to reach

Rs. 8 billion allocated to promote youth entrepreneurship in Koshi Province: CM Karki

SANKHUWASABH: Koshi Province Chief Minister Hikmat Kumar Karki has said