Muglin–Pokhara Khairenitar west section: Blacktopping begins in Jamune



DAMAULI: Blacktopping work has begun in Jamune Bazaar under the Muglin–Pokhara Road Project (West Section).

Of the total 39 kilometers in this section, 36.8 kilometers have already been blacktopped, while the remaining segments are being completed at an accelerated pace.

According to Krishna Kunwar, head of the Muglin–Pokhara Road Project (West Section), a few stretches—including Mauriodar in Myagde, Dulegowda in Shuklagandaki, Vijaypul in Kaski, and the area near Pokhara University—are still awaiting blacktopping.

Out of the 12 bridges planned in this section, 10 have been completed. Similarly, 92 out of 100 culverts have been constructed. The project, which began with a total budget of Rs 7.4 billion, is targeted for completion by the upcoming month of December.

Publish Date : 29 August 2025 23:43 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Tea exports decline through eastern border

BHADRAPUR: Nepali tea exports to India through the eastern border

Nepali Congress forms strategic response team for disaster management

KATHMANDU: The Nepali Congress has formed a 40-member Strategic Response

Nepali Congress demands judicial probe into Sunsari and other incidents

KATHMANDU: The Nepali Congress has called on the government to

Bus-hit sends parked car plunging into Sunkoshi River

KATHMANDU: A car has gone missing after falling into the