Muglin–Pokhara Khairenitar west section: Blacktopping begins in Jamune



DAMAULI: Blacktopping work has begun in Jamune Bazaar under the Muglin–Pokhara Road Project (West Section).

Of the total 39 kilometers in this section, 36.8 kilometers have already been blacktopped, while the remaining segments are being completed at an accelerated pace.

According to Krishna Kunwar, head of the Muglin–Pokhara Road Project (West Section), a few stretches—including Mauriodar in Myagde, Dulegowda in Shuklagandaki, Vijaypul in Kaski, and the area near Pokhara University—are still awaiting blacktopping.

Out of the 12 bridges planned in this section, 10 have been completed. Similarly, 92 out of 100 culverts have been constructed. The project, which began with a total budget of Rs 7.4 billion, is targeted for completion by the upcoming month of December.

Publish Date : 29 August 2025 23:43 PM

Gold price up by Rs 3,500 per tola today

KATHMANDU: The price of gold increased by Rs 3,500 per tola

Nepal Red Cross Society provides food supplies to flood-affected Uttargaya residents

KATHMANDU: The Nepal Red Cross Society (NRCS) has been actively

North Korea and Russia open first road bridge linking countries

MOSCOW: Russia and North Korea have opened the first road bridge

Several highways remain blocked across Nepal due to landslides

KATHMANDU: Several highways across the country remain blocked today due

Two arrested with 162 kg of marijuana in Makawanpur

HETAUDA: Police have arrested two people with 162 kg 794