Muglin–Pokhara Khairenitar west section: Blacktopping begins in Jamune



DAMAULI: Blacktopping work has begun in Jamune Bazaar under the Muglin–Pokhara Road Project (West Section).

Of the total 39 kilometers in this section, 36.8 kilometers have already been blacktopped, while the remaining segments are being completed at an accelerated pace.

According to Krishna Kunwar, head of the Muglin–Pokhara Road Project (West Section), a few stretches—including Mauriodar in Myagde, Dulegowda in Shuklagandaki, Vijaypul in Kaski, and the area near Pokhara University—are still awaiting blacktopping.

Out of the 12 bridges planned in this section, 10 have been completed. Similarly, 92 out of 100 culverts have been constructed. The project, which began with a total budget of Rs 7.4 billion, is targeted for completion by the upcoming month of December.

Publish Date : 29 August 2025 23:43 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Over 146,000 students remain non-graded in SEE results

KATHMANDU: More than 146,000 students who appeared in this year’s

Here’s how students can check SEE results

KATHMANDU: The results of the Secondary Education Examination (SEE) have

PMO says PM Balen Shah briefly left Parliament due to health discomfort

KATHMANDU: The secretariat of Prime Minister Balen Shah has clarified

Jagdish Kharel challenges allegations, vows to quit politics if link to Smart Telecom proven

KATHMANDU: Former Minister for Communications and Rastriya Swatantra Party (RSP)