Ninety percent of Doda River bridge construction completed



KANCHANPUR: Around 90 percent of the construction work on the bridge being built over the Doda River in Kanchanpur has been completed.

According to Harish Prasad Joshi, Information Officer at the Road Division Office in Mahendranagar, the project aims to finish by the end of December. The superstructure of the bridge has already been completed, and work is currently underway to build retaining walls and fill soil on both sides of the bridge, he said.

The total estimated cost of the bridge project is Rs 247.38 million. A contract worth Rs 243.92 million was signed with the Lumbini-Rajendra-Kumar-Shrestha JV for its construction.

Joshi noted that progress may be affected due to limited funding. Only Rs 4 million has been allocated for the current fiscal year, whereas an additional Rs 40 million is required to complete the project.

Locals have long faced difficulties crossing the Doda River in the absence of a bridge, often risking their safety. Once completed, the bridge is expected to greatly ease transportation for residents of Lajhadi, Shuklaphanta, and Krishnapur, said local resident Bachchan Rana.

Publish Date : 23 October 2025 09:05 AM

Nepal’s travel payment reaches Rs 75.74 billion in first four months of fiscal year

KATHMANDU: Nepal’s travel payment rose 11.8 percent to Rs 75.74

China offers 33 scholarships for Nepali students, including MBBS

KATHMANDU: The Government of China has announced a total of

Cabinet approves Rs 14.38 billion concessional loan from ADB

KATHMANDU: The government has decided to accept a concessional loan

Over 2,000 trees felled for Upper Arun Hydropower Project

KATHMANDU: More than 2,000 trees have been cut down in

Newly appointed NPC Vice Chair, member take oath of office

KATHMANDU: Newly appointed Vice Chairperson of the National Planning Commission