Upgrades at TU Cricket Ground face delays



KATHMANDU: Renovation work at the Tribhuvan University Cricket Ground in Kirtipur is ongoing, with efforts focused on installing stadium parapets and floodlights. However, delays in project completion have led the government to impose financial penalties on the contractor.

According to the Ministry of Urban Development, the contractor is now liable to pay a daily penalty of 0.005 percent of the total project cost, amounting to more than Rs. 200,000 per day in compensation.

The penalty came into effect on July 14 after the contractors failed to meet the scheduled deadline.

The contracts were signed in March between the ministry’s Federal Secretariat Construction and Management Office and two joint venture companies.

The BKUI-KCDC BG JV is responsible for constructing the parapets, with a contract worth Rs. 492.5 million, while the Bishan Ishwari JV was contracted for floodlight installation, valued at Rs. 473.7 million.

Under legal provisions, contractors may continue working while paying the daily fine for up to 200 days, equivalent to 10 percent of the total project value. If the work is not completed within that window, the firms risk being blacklisted.

Despite the delays, progress is being made. According to project officials, the contractor has committed to completing the work within a month. Currently, 4,000 seats have been installed, and three out of six floodlight poles have arrived on-site.

In terms of progress, parapet construction has reached 63 percent financially and 77 percent physically, while floodlight installation stands at 29 percent financial and 45 percent physical completion.

default
default
default

Publish Date : 17 July 2025 13:05 PM

Kaski police arrest 27 absconding convicts in a single day

GANDAKI: The District Police Office, Kaski, has arrested 27 absconding

Non-formal education data integrated into EMIS system

KATHMANDU: The Education and Human Resource Development Center under the

Govt warns fertilizer importers against selling substandard chemical fertilizers

KATHMANDU: The Ministry of Agriculture, Forest and Environment has directed

Rhino found dead in Kawasoti maize field

KATHMANDU: A male rhino was found dead at Lokaha Syauli

NAC owes over Rs 55 billion to EPF and CIT

KATHMANDU: Nepal Airlines Corporation (NAC) owes more than Rs 55.47