NEA rules out load shedding, vows long-term solutions



KATHMANDU: Nepal Electricity Authority (NEA) Managing Director Hitendra Dev Shakya has assured that the country will not face a return to load shedding, despite a major power outage on Thursday evening that affected large parts of the country.

Speaking at a press conference to clarify the incident, Shakya attributed the disruption to weather-related technical problems and dismissed rumors of regular power cuts returning.

On Thursday evening at 6:38 PM, electricity supply was disrupted across much of the country.

According to NEA, both circuits of the Dhalkebar-Muzaffarpur 400 kV double circuit transmission line were affected simultaneously due to a storm in the Dhalkebar area.

“Electricity demand is highest in the evening, but due to low domestic production and line tripping, the system becomes unstable,” NEA explained.

Shakya refuted rumors circulating on social media about the return of load shedding. “The claims that load shedding has returned, and we are going back to the days of inverters and candles, are false,” he said. “A tree branch falling on the line caused the issue, which was resolved within about two hours.”

Shakya said that he personally went to the Electricity System Operation Department in Syuchatar to monitor the situation after the outage occurred.

He informed that circuit-2 of the Dhalkebar-Muzaffarpur line resumed operation at 8:08 PM, restoring a smooth power supply.

However, he acknowledged that not all areas received electricity immediately, as trees had fallen on 132 kV, 33 kV, and 11 kV lines in the Dhalkebar West area, damaging poles and conductors.

To prevent similar problems in the future, Shakya said that the NEA will develop immediate, medium-term, and long-term strategies.

Publish Date : 16 May 2025 14:00 PM

Madhav Thapa Risky Photojournalism Award presented to Prabin Kulung Rai

KATHMANDU: The Madhav Thapa Risky Photojournalism Award, established by former

Preparations underway for tiger census in Shuklaphanta National Park

KANCHANPUR: Preparations have been completed for the upcoming tiger census

Rabi to meet PM Sushila Karki after releasing from jail

KATHMANDU: Rastriya Swatantra Party (RSP) Chair Rabi Lamichhane is scheduled

We are moving ahead to hold elections: PM Karki

KATHMANDU: Prime Minister Sushila Karki has said that elections of

Construction of Buddhist Stupa completed in Bhojpur’s Panchdhare

BHOJPUR: The construction of a Buddhist stupa in Bhojpur’s Panchdhare,