Kaligandaki Corridor: Blacktopping of Lasti–Beni section underway



MYAGDI: Blacktopping work has commenced on the Lasti–Beni stretch of the Kali Gandaki Corridor, a key road link connecting Maldhunga–Beni–Mustang with the national highway network.

According to Engineer Bishnu Chapagai, Information Officer at the Beni–Jomsom–Korala Road Project, the blacktopping process from Farse toward Beni began today. “Out of the 13-kilometer-long Maldhunga–Beni road, around two kilometers in the landslide-affected area have already been graded,” he said.

Earlier, approximately five kilometers of the road—from Maldhunga in Kushma Municipality-1, Parbat, to Farse in Jaljala Rural Municipality-8—had already been blacktopped.

A contract worth Rs 528.6 million was signed in April 2021 for widening the Maldhunga–Beni section to 11 meters and completing grading and blacktopping works using modern asphalt technology.

Once completed, the project is expected to significantly improve connectivity, reduce travel time, and boost economic activities along the corridor.

Publish Date : 13 November 2025 09:11 AM

Opposition urges government to seek international expertise for complex disaster rescue

KATHMANDU: Opposition parties have urged the government to seek international

Families question army search for missing Rasuwagadhi hydropower workers

KATHMANDU: Families of employees who went missing after the devastating

27 Bhotekoshi flood victims receiving treatment at Teaching Hospital

KATHMANDU: Twenty-seven people injured in the Bhotekoshi River flood in

UML lawmakers to donate 15 days’ salary to disaster relief fund

KATHMANDU: The CPN-UML has decided to seek the formation of

Nepal-India Border Coordination Committee meeting concludes

BAITADI: The Nepal-India Border Coordination Committee meeting has concluded in