Rahughat Hydropower Project remains incomplete despite second deadline extension



MYAGDI: The 40-megawatt Rahughat Hydropower Project, promoted by Raghuganga Hydropower Ltd., a subsidiary of Nepal Electricity Authority (NEA), has failed to meet its second extended completion deadline.

The Indian contractor Jayaprakash Associates (JP) had signed a Rs 6 billion contract on November 17, 2017, with an initial target to complete the project in 45 months.

After the first deadline passed, a second extension was granted in February 2022, which is now set to expire on June 27. Yet, the project remains incomplete.

So far, the project has achieved 79.5 percent physical progress and 75 percent financial progress. The contractor has now proposed extending the deadline to December 31, 2025.

Rahughat Project Manager Raj Bista informed that the consulting firm Wakfos is currently reviewing the extension request.

Bharat Heavy Electricals Limited (BHEL), responsible for the electromechanical works under a US$ 12.93 million contract signed in Kartik 2076 BS, has also failed to import and install the power house equipment as planned.

The project is being executed under the Engineering Procurement and Construction (EPC) model with a concessional loan of US$ 67 million from the Export-Import Bank of India, and joint funding from the NEA and the Government of Nepal.

Concerns have grown over the prolonged delays. The Government of India, Nepal’s Ministry of Energy, and the NEA have expressed renewed interest in pushing the project forward.

On Jestha 17, Indian Ambassador to Nepal Naveen Srivastava, Energy Secretary Suresh Acharya, and NEA Executive Director Hitendra Dev Shakya visited the project site for monitoring.

During the visit, JP’s manager Harish Agrawal and BHEL’s representative Harsh Bardan formally proposed extending the deadline, citing delays caused by the COVID-19 pandemic, floods, landslides, and scarcity of riverbed construction materials.

Publish Date : 13 June 2025 09:18 AM

Gagan Thapa-led NC leaders reach Election Commission to update party decisions

KATHMANDU: Leaders of the Nepali Congress led by Gagan Thapa

Deuba faction removes Gagan, Bishwa and Mansoor from Nepali Congress website

KATHMANDU: The Sher Bahadur Deuba-led establishment faction of the Nepali

Gen-Z Movement slams bid to shield Rabi Lamichhane, demands rule of law

KATHMANDU: Gen-Z Movement Nepal has strongly objected to what it

UML General Secretary Pokhrel says withdrawal of Rabi Lamichhane case weakens rule of law

KATHMANDU: CPN-UML General Secretary Shankar Pokhrel has said the government’s

Stray dog from Chitwan finds forever home in the US

CHITWAN: A stray dog that once startled an American mother