Suryabinayak-Dhulikhel road expansion progress (Photos)



KATHMANDU: The expansion of the 16-kilometer stretch from Suryabinayak to Dhulikhel along the Araniko Highway to a 6-lane road has gained significant momentum.

The expansion work began in January 2023 with an original completion timeline of 36 months.

The project was divided into two sections: from Suryabinayak in Bhaktapur to Sanga, and from Sanga to Dhulikhel. However, the project has reported only about 30 percent progress so far.

A contract agreement was signed for the expansion of the 7.5-km Suryabinayak-Sanga section for 3.8893 billion rupees, and for the 8.4-km Sanga-Dhulikhel section at 4.564 billion rupees.

According to the Suryabinayak-Dhulikhel, Sindhuli-Bardibas Road Project Office, the expansion work, however, has faced delays due to a budget shortage.

The road, including the main highway and service lanes, is intended to be widened to 6 lanes, but the project has struggled to keep pace with its initial timeline.

Currently, construction of retaining walls on both sides of the road, as well as drains and culverts, is nearing completion.

However, challenges persist, particularly in the Sanga area, where a large bend in the road and a steep cliff below have complicated the construction process.

Publish Date : 01 February 2025 11:37 AM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Rasuwa Floods affect 10 percent of Nepal’s electricity capacity

KATHMANDU: The floods in the Bhotekoshi River in Rasuwa have

Govt coordinating for relief and rescue at national and international levels: Foreign Minister

KATHMANDU: Foreign Minister Shishir Khanal has expressed sorrow over the

Rescue, search and security top priority: PM Shah

KATHMANDU: Prime Minister (PM) Balendra Shah has said the government’s

Rasuwa flood: 403 tourists missing, majority foreign nationals

KATHMANDU: As many as 403 tourists have gone missing following