Sunday, December 14th, 2025

Chinese contractor company of Narayangadh-Butwal road section fails to meet deadline yet again; seeks another extension



NAWALPUR: Failing to meet the deadline of expanding the Narayangadh-Butwal road section under the East-West Highway, the contractor company — China State Construction Engineering Corporation Limited — has sought an extension of the deadline by another nine months.

It should be noted that the construction wor has been completed by only 46 percent in five years since the work began.

The contract of the road project has already been extended twice but the work is far from over according to the Information Officer of Narayangadh-Butwal Road Extension Plan, Eastern Section, Engineer Shiva Khanal.

Out of the total 114 km of road from Narayangadh to Butwal, 65 km of road falls in the eastern section.

According to Khanal, the road expansion work has not been able to accelerate due to the fact that the contractors are not working according to the plans they have made.

“We are constantly putting pressure to work according to the schedule and to complete the project on time”, he said.

The China State Construction Engineering Corporation Limited was given the contract to complete the expansion project to be completed in four years, after starting the work in 2075 B.S.

Meanwhile, contract co-manager of China State Construction Engineering Corporation Limite, Rakesh Jha, said that the road expansion work cannot be completed during the second extension period and that the deadline should be extended by one more year.

The road expansion work was delayed due to various reasons including the current weather that is hampering the black topping of the finish section of the road.

The work of moving water supply and electricity poles as well as 30 KV transmission lines in Siji, Gandakot and Dumkibas areas are yet to be completed, he said.

After the expansion of the existing two-lane road, the highway will be seven by seven meters on both sides.

A service lane of 6 meters each will also be constructed in the market area. Information Officer Khanal said that the 42.7 km section of the road will have four lanes, while the southern section will have three lanes for about five km.

In this section, 12 big bridges and 22 small bridges are under construction.

The construction of this section started with 85 percent loan support from the Asian Development Bank and the total cost of this section is 9.38 billion rupees.

Publish Date : 08 February 2024 07:48 AM

Nepal to send two elephant calves to Qatar

CHITWAN: Two elephant calves born at the Elephant Breeding and

NC Acting President Khadka calls emergency meeting of Nepali Congress CWC

KATHMANDU: The Nepali Congress (NC) has called an emergency meeting

Contracts will be cancelled if work remains unfinished: Minister Ghising

TANAHUN: Minister for Physical Infrastructure and Transport Kulman Ghising has

UML General Convention: Closed session set to begin to elect new leadership

KATHMANDU: A closed session of the 11th General Convention of

Astalaxmi Shakya and Yubaraj Gyawali to step down from UML Central Committee

KATHMANDU: UML Vice Chairs Astalaxmi Shakya and Yubaraj Gyawali have