Seti hydel project begins commercial power generation



KASKI: The Seti Hydropower Project located at Machhapuchchhre Rural Municipality in the district of Kaski has started commercial power generation.

The project with a capacity of 25 megawatts commenced commercial power generation after completing the tests of power plant, interconnection and commissioning.

Chairman of the company Jag Bahadur Pokharel said that the power generated from the project was connected to the system of Nepal Electricity Authority (NEA).

The power generated from the project is supplied to the NEA through its substation at Lahachowk village of the rural municipality.

The total cost of the run of the river project has exceeded Rs 5 billion, it is said.

The water has been supplied to the powerhouse at Chintebagar area through a 6,400-metre-long underground pipeline from Bharabhari site of Seti river in Sardhikhola.

Publish Date : 06 December 2024 12:16 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Nine Foreign Ministry officials among 18 charged in e-passport corruption case

KATHMANDU: Nine officials associated with the Ministry of Foreign Affairs

Over 9,200 tourists visit Koshi Tappu Wildlife Reserve in first 11 months of FY 2025/26

KATHMANDU: A total of 9,242 tourists visited the Koshi Tappu

UML condemns arrest of Vice-Chair Bishnu Paudel, calls it political vendetta

KATHMANDU: The CPN-UML has strongly condemned the arrest of its