Seti hydel project begins commercial power generation



KASKI: The Seti Hydropower Project located at Machhapuchchhre Rural Municipality in the district of Kaski has started commercial power generation.

The project with a capacity of 25 megawatts commenced commercial power generation after completing the tests of power plant, interconnection and commissioning.

Chairman of the company Jag Bahadur Pokharel said that the power generated from the project was connected to the system of Nepal Electricity Authority (NEA).

The power generated from the project is supplied to the NEA through its substation at Lahachowk village of the rural municipality.

The total cost of the run of the river project has exceeded Rs 5 billion, it is said.

The water has been supplied to the powerhouse at Chintebagar area through a 6,400-metre-long underground pipeline from Bharabhari site of Seti river in Sardhikhola.

Publish Date : 06 December 2024 12:16 PM

‘Cross Border Tourism Council’ set to be formed to boost Nepal–India tourism

NEPALGUNJ: A joint platform named the ‘Cross Border Tourism Council’

Parties divided over polls as RSP seeks security guarantee, UML doubts feasibility

KATHMANDU: Sharp divisions among political parties surfaced on Monday over

Oli meets Deuba as all-party talks continue at Singha Durbar

KATHMANDU: While an all-party meeting called by Prime Minister Sushila

MCA-Nepal signs two contracts for road maintenance project

KATHMANDU: MCA-Nepal signed two essential contracts totaling USD 23.66 million

NEPSE falls 13.88 points, turnover declines

KATHMANDU: The Nepal Stock Exchange (NEPSE) index declined by 13.88