Seti hydel project begins commercial power generation



KASKI: The Seti Hydropower Project located at Machhapuchchhre Rural Municipality in the district of Kaski has started commercial power generation.

The project with a capacity of 25 megawatts commenced commercial power generation after completing the tests of power plant, interconnection and commissioning.

Chairman of the company Jag Bahadur Pokharel said that the power generated from the project was connected to the system of Nepal Electricity Authority (NEA).

The power generated from the project is supplied to the NEA through its substation at Lahachowk village of the rural municipality.

The total cost of the run of the river project has exceeded Rs 5 billion, it is said.

The water has been supplied to the powerhouse at Chintebagar area through a 6,400-metre-long underground pipeline from Bharabhari site of Seti river in Sardhikhola.

Publish Date : 06 December 2024 12:16 PM

Gen-Z Movement slams bid to shield Rabi Lamichhane, demands rule of law

KATHMANDU: Gen-Z Movement Nepal has strongly objected to what it

UML General Secretary Pokhrel says withdrawal of Rabi Lamichhane case weakens rule of law

KATHMANDU: CPN-UML General Secretary Shankar Pokhrel has said the government’s

Stray dog from Chitwan finds forever home in the US

CHITWAN: A stray dog that once startled an American mother

Ramesh Kharel says Deuba’s ‘clinging to power’ led to NC split

KATHMANDU: Former Deputy Inspector General of Nepal Police Ramesh Kharel

Five killed as marble-laden truck overturns in Sunsari

KATHMANDU: Five people were killed when a truck carrying marble