Seti hydel project begins commercial power generation



KASKI: The Seti Hydropower Project located at Machhapuchchhre Rural Municipality in the district of Kaski has started commercial power generation.

The project with a capacity of 25 megawatts commenced commercial power generation after completing the tests of power plant, interconnection and commissioning.

Chairman of the company Jag Bahadur Pokharel said that the power generated from the project was connected to the system of Nepal Electricity Authority (NEA).

The power generated from the project is supplied to the NEA through its substation at Lahachowk village of the rural municipality.

The total cost of the run of the river project has exceeded Rs 5 billion, it is said.

The water has been supplied to the powerhouse at Chintebagar area through a 6,400-metre-long underground pipeline from Bharabhari site of Seti river in Sardhikhola.

Publish Date : 06 December 2024 12:16 PM

Arbakuna Orange Farmer Group earns Rs 8.7 million from orange sales

SYANGJA: The Arbakuna Orange Farmer Group in Putalibazaar Municipality-7, Syangja,

Harshal Pathak appointed head coach of Nepal women’s national cricket team

KATHMANDU: The Cricket Association of Nepal (CAN) has appointed Harshal

UML leadership election today; voting postponed to 4 pm due to technical preparations

KATHMANDU: Voting to elect the new leadership of the CPN-UML

Govt terminates 22 stalled irrigation contracts worth Rs 14.23 billion

KATHMANDU: The government has terminated 22 irrigation-related contracts that had

Authorities take action against five firms

KATHMANDU: The Department of Commerce, Supplies and Consumer Protection (DoCSCP)