Seti hydel project begins commercial power generation



KASKI: The Seti Hydropower Project located at Machhapuchchhre Rural Municipality in the district of Kaski has started commercial power generation.

The project with a capacity of 25 megawatts commenced commercial power generation after completing the tests of power plant, interconnection and commissioning.

Chairman of the company Jag Bahadur Pokharel said that the power generated from the project was connected to the system of Nepal Electricity Authority (NEA).

The power generated from the project is supplied to the NEA through its substation at Lahachowk village of the rural municipality.

The total cost of the run of the river project has exceeded Rs 5 billion, it is said.

The water has been supplied to the powerhouse at Chintebagar area through a 6,400-metre-long underground pipeline from Bharabhari site of Seti river in Sardhikhola.

Publish Date : 06 December 2024 12:16 PM

Health of Rabilaxmi Chitrakar showing improvement

KATHMANDU: The health of Rabilaxmi Chitrakar, spouse of former Prime

Minister Kulman Ghising claims completion of 101 projects in 100 days

KATHMANDU: Minister for Physical Infrastructure and Transport, Urban Development, and

Election Commission appoints officials for National Assembly polls, seven provincial offices set up

KATHMANDU: The Election Commission has established provincial offices and appointed

Around 58% of farmers registered under Farmer Registration Program

KATHMANDU: Around 58 percent of farmers across Nepal have been

Consensus on elections emerges, but Oli and Deuba want firm assurances

KATHMANDU: President Ram Chandra Paudel, Prime Minister Sushila Karki and