North South Corridor waiting completion of numerous structures



KATHMANDU: Construction of various bridges along the North-South Corridor roadways is yet to be started though there is a target to complete the Corridor projects in the next two years.

To date, the Kaligandaki corridor awaits the construction of 15 bridges followed by five bridges along the Karnali corridor and four in the Koshi corridor. It is said two bridges along the Koshi corridor have been already over and two are under-construction.

Works are underway to construct 70 meters bridge along the Barun River, according to North-South Corridor project Chief Shyam Bahadur Khadka.

As the Project briefed, the Kalingadaki has already reported the completion of five bridges and some have neared the completion phase.  The bridges measure 60-70 meters.  The Project targets building 14 bridges there in the current fiscal year. “In overall, 15 projects await contracts.”

Among the three corridors, the Karnali reports the lowest progress where the construction of various culverts along with bridges is awaited.  A total of 14 bridges are to be constructed along the Karnali corridor and contracts for nine were finalized till mid-July last year while five are under-construction.

RSS

Publish Date : 28 February 2023 21:31 PM

Gold price drops after recent surge

KATHMANDU: Prices of gold and silver have been fluctuating in

Free eye check-up camp in Ghodaghodi: 75 of 384 people diagnosed with cataracts

KAILALI: A high prevalence of cataracts has been observed in

World Meditation Day observed in Kathmandu (Photos)

KATHMANDU: In line with an announcement by the United Nations,

Impact of erratic weather: Paddy production declines in Bhojpur

BHOJPUR: Paddy production in Bhojpur district has declined this year

Dadeldhura’s Aalitaal Lake shines as new tourist spot

DHANGADHI: Work has begun to promote tourism at Aalitaal, a