cldtfe a'4dfu{sf] sfnf]kq l6s]g tLg dlxgf sf7df8f}F, !^ ebf} . ljZj ;Dkbf ;"rLdf ;"lrs[t af}4gfy If]qsf] cldtfe a'4 dfu{df ;8s sfnf]kq u/]sf] tLg dlxgfd} ag]sf] vf8n . sf7df8f}F dxfgu/kflnsfn] sfnf]kq u/]sf] ;8s tLg dlxgf klg gl6Sbf af}4 If]qsf] 6';fnaf6 dxfFsfn / ;Dkbf dfu{ x'Fb} af}4 r}To k'Ug d'l:sn x'gfsf ;fy} ko{6sdfkm{t g]kfnsf] gsf/fTds ;Gb]z k|jfx eO/x]sf] 5 . tl:a/ M k"0f{k|;fb ld>, /f;;

National

Ranke-Rabi-Bhedetar road sees dismal progress in 50 months

By Khabarhub

March 27, 2023

DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.