Sarangghat ‘substation’ into operation



BANDIPUR: The construction of 33-11 KV Sarangghat substation based in Bandipur Rural Municiplaity-6, Sarangghat of Tanahun has been completed.

The substation was constructed under the Social Development Programme of the 140-MW Tanahun Hydropower Project being constructed by Tanahun Hydropower Ltd, a subsidiary of the Nepal Electricity Authority (NEA).

The transmission lines and substation that were constructed through ‘Tanahun Rural Electrification and Distribution Networking Improvement Project’ implemented by NEA’s Project Management Directorate were brought into operation.

Likewise, the 33-KV transmission line from Marki Chowk Substation based in Anbukhaireni Rural Municipality to Dumre of Bandipur Rural Municipality has been tapped.

As informed, the construction of a 19-km long 33-KV line has been completed to tap the transmission line at Bandipur, Yampaphant to reach it to the Sarangghat substation.

Out of this, a 1,100-meter transmission line has been undergrounded.

The substation and transmission lines were constructed to expand electrification in the project-affected areas of Tanahun district and ensure power supply adequate, reliable and quality.

For the construction of two substations and electrification in Tanahun, a contract was awarded to the East India Industry Waiba Info-tech JV in November 2018.

The project with an estimated cost of around eight million US Dollars was implemented with investment of NEA and subsidy loan of the ADB.

Publish Date : 21 March 2023 13:33 PM

Imports worth Rs 359 billion enter Nepal through Birgunj customs in five months

BIRGUNJ: Goods and commodities worth Rs 359.23 billion have been

Pokhara Metropolis to remove roadside workshops, garages from major roads

POKHARA: Pokhara Metropolitan City has announced a plan to remove

Rabi Lamichhane–Balen Shah meeting sparks speculation of political alignment

KATHMANDU: A meeting between Rastriya Swatantra Party (RSP) Chair Rabi

UML holds nationwide joint meeting to disseminate message of 11th national convention

KATHMANDU: The CPN-UML is holding a joint meeting of all

Preparations underway for Budhigandaki ‘A’ and ‘B’ hydropower projects

GORKHA: Preparatory work has begun for the construction of the