Seti hydropower project in final stage



KASKI: The work of the 25 MW Seti river hydropower project has reached its final stage.

The project is being built in Sardikhola of Machhapuchchhe Rural Municipality-2.

The construction of the hydropower project that started from Bhadra, 2077 BS has seen 90 percent of the work completed so far.

Executive Chair of Vision Lumbini Energy Company Limited, Jagat Bahadur Pokharel, said that all the works towards construction of civil, hydro mechanical, electro mechanical and transmission line (transmission line) of the project have reached the final stage.

The project on the Seti river will be completed by coming December.

The construction work was delayed by one year due to the Corona Virus pandemic, said Pokharel.

“Within the next five months, the project will be completed and electricity will be produced.”

A total of Rs 5 billion has been invested in the Seti hydropower project, with various banks and financial institutions investing Rs 3.5 billion.

The electricity produced by the Seti project will be connected to the substation of Nepal Electricity Authority in Lahachowk located at a distance of four kilometers.

The transmission line is being constructed from the power house to the substation.

Publish Date : 04 June 2023 09:35 AM

Delays, apathy and mismanagement leave millions of Pakistanis stranded in Gulf crisis

Delays, poor coordination, and lax attitude, added to the lack

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Deputy Speaker Thakur takes oath of office and secrecy

KATHMANDU: Newly elected Deputy Speaker of the House of Representatives,

Stakeholders stress urgent need to improve Kathmandu traffic management

KATHMANDU: Stakeholders have emphasized the need for improved traffic management

Nepal to host UAE for two-match T20I series ahead of CWC League 2

KIRTIPUR: The Cricket Association of Nepal (CAN) has announced that